Knowee
Questions
Features
Study Tools

X, Y and Z can complete a job in 10 days, 12 days, and 15 days respectively. They started working together and after some days, Y left. The remaining work was completed by X and Z. A total of ₹24,000 were paid as wages to the three. The wages paid to X were ₹8,000 more than those paid to Y. After how many days did Y leave?

Question

X, Y and Z can complete a job in 10 days, 12 days, and 15 days respectively. They started working together and after some days, Y left. The remaining work was completed by X and Z. A total of ₹24,000 were paid as wages to the three. The wages paid to X were ₹8,000 more than those paid to Y. After how many days did Y leave?

🧐 Not the exact question you are looking for?Go ask a question

Solution

To solve this problem, we need to first understand the rate at which each person works.

  1. X can complete the job in 10 days, so X's work rate is 1/10 of the job per day.
  2. Y can complete the job in 12 days, so Y's work rate is 1/12 of the job per day.
  3. Z can complete the job in 15 days, so Z's work rate is 1/15 of the job per day.

When they work together, their combined work rate is 1/10 + 1/12 + 1/15 = 0.1833 of the job per day.

We know that the total wages paid were ₹24,000, and X was paid ₹8,000 more than Y. Let's denote Y's wage as W. Then X's wage is W + ₹8,000, and Z's wage is ₹24,000 - W - (W + ₹8,000) = ₹16,000 - W.

The wages are proportional to the amount of work done, so W/(W + ₹8,000) = (1/12) / (1/10), which gives us W = ₹9,600. Therefore, X was paid ₹17,600 and Z was paid ₹6,800.

Now, let's denote the number of days Y worked as D. Then X and Z worked together for (total work / combined work rate of X and Z) - D days.

We know that the total work is 1 (as it's one job), and the combined work rate of X and Z is 1/10 + 1/15 = 0.1667 of the job per day.

So, D = (1 / 0.1833) - (1 / 0.1667) = 5.46 days.

Therefore, Y left after approximately 5 or 6 days.

This problem has been solved

Similar Questions

X and Y can do a piece of work in 20 days and 12 days respectively. X started the work alone and then after 4 days Y joined him until the completion of the work. How long did the work last?

X can do a piece of work in 8 days, Y can do it in 10 days and Z can do it in 20 days. In how many days can X, Y and Z together complete the work?3 (7/11) days5 days4 (2/5) days6 days

A can do a job in 10 days and B in 15 days. They are working on a project of Rs. 1500. If A and B worked for 5 days and rest work is finished by C in 2 days. What will be the daily wages of C

Ramesh can complete a work in 20 days. Mohan is 66.67% as efficient as Ramesh. Mohan and Ramesh begin to work together. Ramesh leaves after working for some days. The remaining work is completed by Mohan in 10 days. After how many days does Ramesh leave the work?

elect the correct answerA can do a piece of work in 90 days, B in 40 days and C in 12 days. They work for a day each in turn i.e., first day A does it alone, B does it the second day and C the third day. After that A does it for another day, and so on. After finishing the work they get Rs. 240. If the wages are divided in proportion to the work done by them, find what each will getOptionsA Rs.22, B Rs.50 and C Rs. 132A Rs. 24, B Rs.54 and C Rs. 162A Rs. 26, B Rs.52 and C Rs. 142A Rs. 20, B Rs. 44 and C Rs.182

1/3

Upgrade your grade with Knowee

Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.