A takes 5 days more than B to do a certain job and 9 days more than C; A and B can do the job in the same time as C. How many days A would take to do it?Options5152010

Question

A takes 5 days more than B to do a certain job and 9 days more than C; A and B can do the job in the same time as C. How many days A would take to do it?Options5152010

🧐 Not the exact question you are looking for?Go ask a question

Solution

Let's denote the time it takes for A, B, and C to complete the job as a, b, and c respectively.

From the problem, we know that:

  1. a = b + 5 (A takes 5 days more than B to do a certain job)
  2. a = c + 9 (A takes 9 days more than C to do the job)
  3. a + b = c (A and B can do the job in the same time as C)

We can substitute equations 1) and 2) into equation 3) to get:

b + 5 + b = c + 9 2b = c + 4 c = 2b - 4

Substitute c into equation 2):

a = 2b - 4 + 9 a = 2b + 5

Since a = b + 5, we can set 2b + 5 = b + 5 and solve for b:

b = 0

Substitute b = 0 into a = b + 5:

a = 0 + 5 a = 5

So, A would take 5 days to do the job. The answer is 5.

This problem has been solved

Similar Questions

A, B and C can do a work in 5 days, 10 days and 15 days respectively. They started together to do the work but after 2 days A and B left. C did the remaining work (in days)

Select the correct answerA can do a piece of work in 5 days, B can do it in 10 days. With the help of C, they finish the work in 2 days. In how many days C alone can do the whole work?Options3 days5 days6 days4 days

A and B together can complete a task in 10 days, while B and C together can complete the same task in 15 days. If A, B, and C work together, how long will it take to complete the task?A)  5 days B) 6 days C) 7.5 days D) 8 days

A can finish one-third of a work in 5 days, B can finish 2/5th of the same work in 10 days and C can finish 75% of the same work in 15 days. They work together for 6 days; The remaining work will be finished by B alone in?Options5 days3 days2.5 days1.5 days

A and B together can complete a work in 12 days, B and C together can complete the same work in 8 days and A and C together can complete it in 16 days. In total, how many days do A, B and C together take to complete the same work?Options3 5/123 9/137 5/127 5/13

1/3

Upgrade your grade with Knowee

Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.