Janitor Supply produces an industrial cleaning powder that requires 50 grams of material at $0.40 per gram and 0.15 direct labor hours at $14.00 per hour. Overhead is applied at the rate of $18 per direct labor hour. What is the total standard cost for one unit of product that would appear on a standard cost card?Multiple Choice$22.10.$22.70.$35.00.$4.80.$24.80.

Question

Janitor Supply produces an industrial cleaning powder that requires 50 grams of material at 0.40pergramand0.15directlaborhoursat0.40 per gram and 0.15 direct labor hours at 14.00 per hour. Overhead is applied at the rate of 18perdirectlaborhour.Whatisthetotalstandardcostforoneunitofproductthatwouldappearonastandardcostcard?MultipleChoice18 per direct labor hour. What is the total standard cost for one unit of product that would appear on a standard cost card?Multiple Choice22.10.22.70.22.70.35.00.4.80.4.80.24.80.

🧐 Not the exact question you are looking for?Go ask a question

Solution

To calculate the total standard cost for one unit of product, we need to add up the cost of material, labor, and overhead.

  1. Material cost: 50 grams of material at 0.40pergram=500.40 per gram = 50 * 0.40 = $20.00

  2. Labor cost: 0.15 hours at 14.00perhour=0.1514.00 per hour = 0.15 * 14.00 = $2.10

  3. Overhead cost: Overhead is applied at the rate of 18perdirectlaborhour.So,for0.15hours,theoverheadcost=0.1518 per direct labor hour. So, for 0.15 hours, the overhead cost = 0.15 * 18 = $2.70

Adding all these up, the total standard cost for one unit of product = 20.00(material)+20.00 (material) + 2.10 (labor) + 2.70(overhead)=2.70 (overhead) = 24.80

So, the correct answer is $24.80.

This problem has been solved

Similar Questions

A company produces batches of 1,500 units. Each batch requires 60 machine hours. The overhead is applied at a rate of $30 per machine hour. If the direct materials cost $3,000 and the direct labor costs $2,700 per batch, what is the total cost of the batch and the cost per unit?Question 17Answera.Total cost: $7,500, Cost per unit: $5b.Total cost: $7,200, Cost per unit: $4.80c.Total cost: $6,000, Cost per unit: $4d.Total cost: $6,500, Cost per unit: $4.33

Given the following, the standard cost of this item is $ per unit. (Enter your answer as a whole number.)   Direct materials per unit 2 poundsDirect material cost$2.50 per poundDirect labor per unit.75 hoursDirect labor rate$16.00 per hourVariable overhead rate$8.00 per hour

During its first month of operations, a manufacturer incurs the following costs (in dollars) related to activities within its factory:Direct materials $15,000Direct labor $30,000Manufacturing overhead $40,000What amount should be reported as cost of goods sold on the income statement if 5,000 units are produced and 4,000 are sold? $56,000 $68,000 $70,000 $85,000

Direct materials are $15 per unit; direct labor is $7 per unit and variable overhead costs are $2 per unit. If total product costs are $27, what are fixed costs per unit?Multiple choice question.$3$30$24

ill in the Blank QuestionFill in the blank question.A manufacturing company has variable overhead costs of $2.50 per unit and fixed costs of $5,000 per month. Each unit requires 4 hours of direct labor and the company expects to produce 2,000 units each month. The standard overhead rate will be $ per direct labor hour.