A job was budgeted to require 2 hours of labor per unit at $11.00 per hour. The job consisted of 8,500 units and was completed in 16,000 hours at a total labor cost of $189,100. What is the total direct labor variance?
Question
A job was budgeted to require 2 hours of labor per unit at 189,100. What is the total direct labor variance?
Solution
To calculate the total direct labor variance, we need to first calculate the standard cost, actual cost, and then the difference between them.
-
Calculate the Standard Cost: The standard cost is the cost that was originally expected or budgeted for the job. It is calculated by multiplying the budgeted labor hours per unit by the budgeted cost per labor hour, and then multiplying that by the total number of units.
Standard Hours = 2 hours/unit * 8,500 units = 17,000 hours Standard Rate = 11.00/hour = $187,000
-
Calculate the Actual Cost: The actual cost is the cost that was actually incurred to complete the job. In this case, it is given as $189,100.
-
Calculate the Total Direct Labor Variance: The total direct labor variance is the difference between the standard cost and the actual cost.
Total Direct Labor Variance = Actual Cost - Standard Cost = 187,000 = $2,100
So, the total direct labor variance is $2,100. This is a unfavorable variance, as the actual cost was higher than the standard cost.
Similar Questions
Given the following information, calculate the direct labor price variance. Actual production in units17,000Standard labor cost per unit1/2 hour @ $20 per hourActual cost for labor$216,750 for 12,750 hoursMultiple choice question.$38,250 favorable$38,250 unfavorable$72,750 unfavorable$72,750 favorable
Use the following data to find the direct labor rate variance if the company produced 3,500 units during the period. Direct labor standard (4 hours @ $12/hour) $ 48 per unitActual hours worked 12,250 Actual rate per hour $ 12.50 Multiple Choice$21,000 favorable.$6,125 unfavorable.$7,000 unfavorable.$14,875 favorable.$7,000 favorable.
XYZ Company makes one product and has calculated the following amounts for direct labor: AH x AR = $84,000; AH x SR = $83,000; SH x SR = $85,000. Compute the direct labor cost variance.Multiple choice question.$2,000 F$1,000 U$2,000 U$1,000 F
A planning budget called for 500 units to be produced and total direct labor cost of $7,500. Actual production was 600 units and actual direct labor cost was $9,300. The spending variance is Blank______.Multiple choice question.$300 F$1,800 U$300 U$1,500 F$1,500 U
Compute the direct labor rate and efficiency variances.
Upgrade your grade with Knowee
Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.