If A takes half as long to do a piece of work as B takes and if C does it in the same time as A and B together and if all three working together would take 7 days, then how long would each take separately?Marks : 2Negative Marks : 0Answer here21, 42, 1414, 35, 2114, 42, 4942, 35, 49

Question

If A takes half as long to do a piece of work as B takes and if C does it in the same time as A and B together and if all three working together would take 7 days, then how long would each take separately?Marks : 2Negative Marks : 0Answer here21, 42, 1414, 35, 2114, 42, 4942, 35, 49

🧐 Not the exact question you are looking for?Go ask a question

Solution

Let's denote the amount of work as W.

  1. If A takes half as long to do a piece of work as B takes, then A does twice as much work in the same time as B. So, if B does W in b days, A does W in a = b/2 days.

  2. If C does it in the same time as A and B together, then C does W in c = a + b days.

  3. If all three working together would take 7 days, then 1/a + 1/b + 1/c = 1/7.

Substituting a = b/2 and c = a + b into the equation, we get 2/b + 1/b + 1/(b + 2b/2) = 1/7, which simplifies to 3/b + 1/(3b/2) = 1/7.

Solving this equation for b, we get b = 14 days. Then a = b/2 = 7 days and c = a + b = 21 days.

So, A would take 7 days, B would take 14 days, and C would take 21 days to do the work separately.

This problem has been solved

Similar Questions

A can do a piece of work in 4 hours. B and C can do the same piece of work together in 3 hours, while A and C together can do it in 2 hours. How long will B alone take to do it?Marks : 1Negative Marks : 0Answer here12638

9) A & B can do a piece of work in 72 days, B & C can do it in 120 days and A & C can do in in 90 days. In how many days all three together can do the work?

A and B together can complete a task in 10 days, while B and C together can complete the same task in 15 days. If A, B, and C work together, how long will it take to complete the task?A)  5 days B) 6 days C) 7.5 days D) 8 days

A takes twice as much time as B or thrice as much time as C to finish a piece of work. Working together, they can finish the work in 2 days. B can do the work alone in:4 days6 days8 days12 days

A takes three times as long as B and C together to do a job. B takes four times as long as A and C together to do the work. If all the three, working together can complete the job in 24 days, then the number of days. A alone will take to finish the job is

1/3