The meeting notes state that training will happen in two phases—one for managers and one for staff. Which of the following three-point time estimates would you choose for fully training the team (including planning, training the managers, and training the staff at each location)?1 pointOptimistic: 2 days; Most Likely: 1 day; Pessimistic: 4 daysOptimistic: 15 days; Most Likely: 30 days; Pessimistic: 45 daysOptimistic: 20 days; Most Likely: 14 days; Pessimistic: 10 daysOptimistic: 10 days; Most Likely: 14 days; Pessimistic: 21 days

Question

The meeting notes state that training will happen in two phases—one for managers and one for staff. Which of the following three-point time estimates would you choose for fully training the team (including planning, training the managers, and training the staff at each location)?1 pointOptimistic: 2 days; Most Likely: 1 day; Pessimistic: 4 daysOptimistic: 15 days; Most Likely: 30 days; Pessimistic: 45 daysOptimistic: 20 days; Most Likely: 14 days; Pessimistic: 10 daysOptimistic: 10 days; Most Likely: 14 days; Pessimistic: 21 days

...expand
🧐 Not the exact question you are looking for?Go ask a question

Solution

The three-point time estimate you choose for fully training the team would depend on the complexity of the training, the number of managers and staff to be trained, and the number of locations. However, based on the information provided, the most reasonable estimate seems to be:

Optimistic: 10 days; Most Likely: 14 days; Pessimistic: 21 days

This estimate seems to allow a reasonable amount of time for planning, training the managers, and training the staff at each location. The other estimates either seem too short (2 days, 1 day, 4 days) or too long (15 days, 30 days, 45 days) for this process. The estimate of 20 days, 14 days, 10 days is not logical as the optimistic estimate is higher than the most likely estimate, which is in turn higher than the pessimistic estimate.

This problem has been solved

Similar Questions

On what does the recommended time (duration) of an endurance training workout depend?Group of answer choicesintensityfrequencymodespecificity

Which of the measures involved in “three-point” time estimations is based on how long the task usually takes under normal circumstances, with only slight adjustments to the best-case scenario?1 pointOptimistic time estimatesPessimistic time estimatesMost likely time estimatesPlanning time estimates

Question 8Which of the measures involved in “three-point” time estimations express how long you hope the task will take, assuming everything goes as planned?1 pointMilestone time estimatesPlanning time estimatesOptimistic time estimatesMost likely time estimates

During the training you will have to deadlines to meet while completing tasks. You realise that you will NOT be able to complete your task on time THREE days before the deadline. How will you approach this and what actions will you take?

As part of the planning process, a PM is estimating duration for a part-time resource’s task. The PM is assigning the team member a 24-hour task. If the team member is working half time, how many calendar days should the PM plan for the task to get completed?Three daysFour daysSix daysEight days