Question
Select the correct answerA can do a piece of work in 8 days and B can do it in 10 days separately. How many days would it take for both A and B to finish the same work together?Options33/841/1042/1140/9
Solution
To solve this problem, we first need to find the rate at which A and B can complete the work.
- A can complete the work in 8 days, so A's rate of work is 1/8 of the work per day.
- B can complete the work in 10 days, so B's rate of work is 1/10 of the work per day.
When A and B work together, their rates of work are added. So, the combined rate of A and B is 1/8 + 1/10 = 5/40 + 4/40 = 9/40 of the work per day.
Therefore, to find out how many days it would take for both A and B to finish the work together, we divide the total work (which is 1) by their combined rate, which is 9/40.
So, the time it would take is 1 / (9/40) = 40/9 days.
So, the correct answer is 40/9.
Similar Questions
Select the correct answerA can complete 1/3 of a work in 5 days and B, 2/5 of the work in 10 days. In how many days both A and B together can complete the work?Options7 1/2days9 3/8 days10 days8 4/5days
Select the correct answerA and B under took a work for Rs. 880. A got Rs. 240 more than B When the work together, B takes 12 days more than A, when they work individually. In how many days A and B working together can do the whole work?Options11.1818181810.181818189 2/1112.10526316
Select the correct answerA takes 10 days less than the time taken by B to finish a piece of work. If both A and B can do it in 12 days, then the time taken by B alone to finish the work is?Options27 days30 days20 days25 days
Select the correct answerA can do 7/8 of work in 28 days, B can do 5/6 of the same work in 20 days. The number of days they will take to complete if they do it together is?Options15 7/3 days14 5/7 days13 5/7 days17 3/5 days
Select the correct answerA and B together can finish a work in 6.75 days. A alone can finish the same work in 9 days. In how many days will B alone finish the work?Options27 days18 days35 days36 days
Upgrade your grade with Knowee
Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.