Knowee
Questions
Features
Study Tools

Which of the following will occur if the project's critical path is impacted by time or effort overruns?a.)The project will not be completed in time.b.)The project manager can assume the critical path will not change.c.)The project will need to have its budget decreased.d.)The project manager should refuse to establish a new critical path.

Question

Which of the following will occur if the project's critical path is impacted by time or effort overruns?a.)The project will not be completed in time.b.)The project manager can assume the critical path will not change.c.)The project will need to have its budget decreased.d.)The project manager should refuse to establish a new critical path.

🧐 Not the exact question you are looking for?Go ask a question

Solution

a.) The project will not be completed in time.

The critical path of a project is the sequence of tasks that must be completed on time for the entire project to be completed on time. If there are time or effort overruns on these tasks, it will directly impact the project completion time. Therefore, if the project's critical path is impacted by time or effort overruns, the project will not be completed in time.

The other options are not correct because:

b.) The project manager cannot assume the critical path will not change. In fact, if there are time or effort overruns, the project manager will likely need to reassess and potentially change the critical path.

c.) The project will not necessarily need to have its budget decreased. Overruns on the critical path could lead to increased costs, not decreased.

d.) The project manager should not refuse to establish a new critical path. If the current critical path is no longer viable due to overruns, a new critical path may need to be established.

This problem has been solved

Similar Questions

Which statement about the project critical path is true?The critical path always has zero total float, and it shows the earliest possible time to complete the projectThe critical path can have zero, positive, or negative float.A project can have only one critical pathThe critical path consumes the biggest portion of the project budget compared to other paths

What is the significance of a critical path?Question 15Answera.The critical path reveals the shortest and longest paths and their differenceb.The critical path shows the number of available float in the projectc.Activities in the critical path are critical activities for achieving project objectivesd.The activities in the critical path have the highest number of float, showing the amount of time those activities can be delayede.When an activity in the critical path is delayed, the entire project will be delayed

Which path duration is considered as the project completion timea.Shortest pathb.Longest Pathc.Most likely pathd.None of the given options

Critical path method is suitable for _____________ project schedulesa.Optimizingb.Minimisingc.Maximizationd.None of the given options

Which of the following does NOT affect a time estimate?Effort estimatesSchedule dependenciesCommunication requirementsEquipment availability

1/3

Upgrade your grade with Knowee

Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.