Select all that applyCritical chain project management (CCPM) overcomes which obstacles introduced by padded estimates?Multiple select question.Parkinson's lawresource smoothingstudent syndromeself-protection
Question
Select all that applyCritical chain project management (CCPM) overcomes which obstacles introduced by padded estimates?Multiple select question.Parkinson's lawresource smoothingstudent syndromeself-protection
Solution
Critical chain project management (CCPM) is designed to address several issues that can arise in project management, including:
-
Parkinson's Law: This law states that "work expands to fill the time available for its completion." In project management, this can lead to inefficiencies as tasks take longer than necessary simply because the time is available. CCPM addresses this by using buffer management instead of deadlines for individual tasks, which can help to ensure that work is completed efficiently.
-
Student Syndrome: This refers to the tendency to start tasks late, similar to how a student might put off studying until right before an exam. CCPM addresses this by scheduling tasks back-to-back without buffers in between, which encourages work to start immediately when a task becomes available.
-
Self-Protection: This refers to the tendency to add padding to task duration estimates to account for potential issues that might arise. This can lead to inflated project timelines and inefficiencies. CCPM addresses this by using a project buffer to account for uncertainties, which can help to reduce the need for individual task padding.
Therefore, the correct answers are Parkinson's law, student syndrome, and self-protection. Resource smoothing is not directly addressed by CCPM.
Similar Questions
Select all that applyWhat are reasons that projects with padding may still come in late?Multiple select question.Parkinson's LawUnderestimates of activity timeSelf-protection
Select all that applyPriorities are the most significant source of conflict in which project phase(s)?Multiple select question.planningdeliveringexecutingdefining
compares it against the plan to identify variances so the PM can take corrective actions to keep the project on track while considering the triple constraints: scope, time, and costs.TrueFalse
What are the four main project cost drivers? Choose any four Fixed costs Risk allowance costs Value related costs Overhead costs Time related costs Quality related costs
Which of the following is not a major type of project selection criteria?Select an answer:NPVPBPFRBIRR
Upgrade your grade with Knowee
Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.