Knowee
Questions
Features
Study Tools

A and B can do a work in 30 days. If A worked twice as fast and B worked one-fourth as efficiently as he usually does, the work would still be completed in 30 days. Find the time taken (in days) by A alone to do the work.

Question

A and B can do a work in 30 days. If A worked twice as fast and B worked one-fourth as efficiently as he usually does, the work would still be completed in 30 days. Find the time taken (in days) by A alone to do the work.

🧐 Not the exact question you are looking for?Go ask a question

Solution

Let's solve this step by step:

Step 1: Let's assume the total work to be done is 1 unit. So, A and B together can do this 1 unit of work in 30 days. Therefore, their combined work rate is 1/30 units per day.

Step 2: Now, if A works twice as fast and B works one-fourth as efficiently, the work is still completed in 30 days. This means their new combined work rate is also 1/30 units per day.

Step 3: Let's denote the work rate of A as 'a' and that of B as 'b'. So, from step 1, we have a + b = 1/30.

Step 4: From step 2, we have 2a + b/4 = 1/30.

Step 5: We can solve these two equations to find the values of 'a' and 'b'. Multiplying the second equation by 4, we get 8a + b = 4/30. Subtracting the first equation from this, we get 7a = 3/30, so a = 3/210 = 1/70.

Step 6: So, A alone can do the work in 70 days.

This problem has been solved

Similar Questions

when working alone A takes 24 more days than time taken by A and B together to finish certain work. If A is 50% more efficient than B, then find the time taken by B to finish the work alone.

A takes twice as much time as B or thrice as much time as C to finish a piece of work. Working together, they can finish the work in 2 days. B can do the work alone in:4 days6 days8 days12 days

Select the correct answerA, B and C together can finish a piece of work in 30 days. If A and C is twice efficient than B. A and B is thrice efficient than C in how many days A alone can complete the work?Options84 days80 days75 days72 days

A and B together can complete a piece of work in 35 days, while A alone can complete it in 60 days. So, B alone can complete the work in how many days?

B is twice efficient than A and the total time taken to complete the work by both A and B together is 22 days. Find thenumber of days taken by B to complete the work alone.

1/3

Upgrade your grade with Knowee

Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.