Due to resource-levelling, the float/slack of non-critical activities can decrease.Group of answer choicesTrueFalse

Question

Due to resource-levelling, the float/slack of non-critical activities can decrease.Group of answer choicesTrueFalse

🧐 Not the exact question you are looking for?Go ask a question

Solution

True. Resource leveling is a technique in project management that is used to examine unbalanced use of resources (usually people or equipment) over time, and for resolving over-allocations or conflicts. When resource leveling is applied to a project, it can often cause the slack or float time of non-critical activities to decrease. This is because resources are shifted to maintain a balance, which can result in non-critical

This problem has been solved

Similar Questions

Resource levelling has the potential of turning non-critical activities into critical activities. Group of answer choicesTrueFalse

Activities with negative Total Float are considered critical.TrueFalse

During the resource levelling process, it is not important to maintain the logical relationship of project activities. Group of answer choicesTrueFalse

New critical path/paths might arise due to resource levelling .Group of answer choicesTrueFalse

For resource constrained project, the duration of the project might have to be increased in order to improve resource utilization.Group of answer choicesTrueFalse