Due to resource-levelling, the float/slack of non-critical activities can decrease.Group of answer choicesTrueFalse
Question
Due to resource-levelling, the float/slack of non-critical activities can decrease.Group of answer choicesTrueFalse
Solution
True. Resource leveling is a technique in project management that is used to examine unbalanced use of resources (usually people or equipment) over time, and for resolving over-allocations or conflicts. When resource leveling is applied to a project, it can often cause the slack or float time of non-critical activities to decrease. This is because resources are shifted to maintain a balance, which can result in non-critical
Similar Questions
Resource levelling has the potential of turning non-critical activities into critical activities. Group of answer choicesTrueFalse
Activities with negative Total Float are considered critical.TrueFalse
During the resource levelling process, it is not important to maintain the logical relationship of project activities. Group of answer choicesTrueFalse
New critical path/paths might arise due to resource levelling .Group of answer choicesTrueFalse
For resource constrained project, the duration of the project might have to be increased in order to improve resource utilization.Group of answer choicesTrueFalse