Which of the following operations would be least suited to a fixed-position layout?Group of answer choicesfast-food restaurantGrand piano tuning specialist servicesOperating theatre in a hospitalBuilding a bridge over a valley

Question

Which of the following operations would be least suited to a fixed-position layout?Group of answer choicesfast-food restaurantGrand piano tuning specialist servicesOperating theatre in a hospitalBuilding a bridge over a valley

🧐 Not the exact question you are looking for?Go ask a question

Solution

The operation least suited to a fixed-position layout would be a fast-food restaurant.

Here's why:

  1. Fixed-position layout: This is a type of operation layout where the product or project remains stationary while workers and equipment come to the site. This layout is typically used for large, complex projects like construction, shipbuilding, or hospital operating theatres.

  2. Fast-food restaurant: In a fast-food restaurant, the operation involves preparing and serving food quickly. This requires a flexible layout that allows for efficient movement of staff and materials, and can adapt to changes in menu, customer flow, or other variables. A fixed-position layout would not be suitable because it would limit the ability to adjust to these changes.

  3. Grand piano tuning specialist services: This could potentially work with a fixed-position layout, as the specialist could travel to the location of the piano. However, it's not as inherently tied to a fixed location as the other examples.

  4. Operating theatre in a hospital: This is a perfect example of a fixed-position layout. The patient (the "project") stays in one place while the surgical team (the "workers") and the medical equipment come to the patient.

  5. Building a bridge over a valley: This is another example of a fixed-position layout. The bridge (the "product") is stationary while the construction crew and equipment move to the site.

So, out of these options, a fast-food restaurant would be least suited to a fixed-position layout.

This problem has been solved

Similar Questions

Multiple Choice QuestionThe layout that requires production to be broken down into relatively simple tasks assigned to workers, who are usually positioned along an assembly line is a ______ layoutMultiple choice question.fixed-positionproductprocessintermittent

_____ is a significant question because, once the decision has been made and implemented, the firm must live with it due to the high costs involved.Multiple choice question.Fixed-position layoutProcess layoutContinuous manufacturing organizationFacility location

A firm manufactures custom-made furniture based on customer specifications. Which of the following facilities layouts would best suit the firm's needs?Multiple Choiceproduct layoutfixed-position layoutprocess layoutsequential layoutflexible manufacturing layout

Items that are produced that are difficult to move often use which type of facility layout technique?Multiple Choicecellular modular layoutprocess layoutproduct layoutboth product and process layoutfixed position layout

Which of the following is a potential disadvantage of functional layout? Group of answer choicesrequire more equipmentComplex flow can be difficult to controlwork can be very repetitiveLow mix flexibility

1/3

Upgrade your grade with Knowee

Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.