The variable overhead efficiency variance compares the hours times the standard rate with the standard hours allowed for the actual output times the rate
Question
The variable overhead efficiency variance compares the hours times the standard rate with the standard hours allowed for the actual output times the rate
Solution
The variable overhead efficiency variance is a measure used in management and cost accounting to assess the efficiency of a company's use of variable overhead based on the standard cost of labor hours. Here's how it's calculated:
-
Determine the standard hours allowed for the actual output: This is the amount of time that should have been used to produce the actual output. It's calculated by multiplying the actual output by the standard hours per unit.
-
Calculate the standard cost of these hours: This is done by multiplying the standard hours allowed for the actual output by the standard variable overhead rate.
-
Determine the actual hours used: This is the actual amount of time used to produce the output.
-
Calculate the standard cost of these actual hours: This is done by multiplying the actual hours used by the standard variable overhead rate.
-
Subtract the standard cost of the actual hours used (step 4) from the standard cost of the standard hours allowed for the actual output (step 2). This gives you the variable overhead efficiency variance.
If the variance is positive, it means that less time was used than expected (i.e., efficiency was higher than expected). If the variance is negative, it means that more time was used than expected (i.e., efficiency was lower than expected).
Similar Questions
A variable overhead budget variance is further analyzed into a variable overhead (price/rate/spending) variance and a variable overhead (usage/efficiency) variance.
The overhead variance is the difference between:Multiple choice question.actual total overhead and the standard overhead budgetedactual total overhead and the standard overhead appliedbudgeted overhead and standard overhead applied
When machine-hours are used as an overhead cost-allocation base, the most likely cause of a favorable variable overhead spending variance is
Compute the direct labor rate and efficiency variances.
abor variance analysis focuses on:a.Variations in the quantity of labor hours usedb.Variations in the wage ratec.Variations in the material costd.Variations in the overhead costsClear my choice