What are the main statuses used on a Kanban board? Select all that apply. 1 pointPlanningIn progressDoneTo do

Question

What are the main statuses used on a Kanban board? Select all that apply. 1 pointPlanningIn progressDoneTo do

🧐 Not the exact question you are looking for?Go ask a question

Solution

The main statuses used on a Kanban board are:

  1. To do
  2. In progress
  3. Done

Planning is not typically a status used on a Kanban board, but it could be part of the process before tasks are added to the "To do" column.

Similar Questions

What are the three columns on the most basic Kanban board?Planning, Sharing, and LearningTo Do, In Progress, and CompleteBudgeting, Review, and DeploymentBacklog, Work In Progress, and Development

Which of the following is NOT an element of a Kanban board?commitment pointsprint backlogcardswork in progress limitdelivery pointcolumns

Question 4What is a kanban board?1 pointA kanban board is made up of multiple project management tools.A method for tracking planned items and showing progress as items are moved across the board.A parking lot for issues to be dealt with laterColored sticky notes, placed on a board to show patterns in software bugs

Identify one purpose of a Kanban board.display issues in the current sprintmeasure team velocitysee the timeline for estimated workhelp identify blockers and dependenciesThis item can be moved. Use the space bar to grab it.Next

When a kanban team member is ready to work on a new issue in the standard Jira kanban workflow, which one of the following is usually true?1 pointAny issue from the backlog is pulled to the "in progress" column.A planning meeting should be called.The issue at the top of the "selected for development" column is pulled to the "in progress" column.

1/3

Upgrade your grade with Knowee

Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.