Jason is a project manager and has to deliver bad news to the stakeholders.Which of the following is representative of effective communication?a.)Jason contacts the stakeholders before he contacts the project sponsor.b.)It is best for Jason to deliver the bad news through email to avoid confrontation with the stakeholder.c.)Jason emphasizes that the blame is on another team member when he delivers the news.d.)Along with the bad news, Jason should make some recommendations on how to resolve the issue.
Question
Jason is a project manager and has to deliver bad news to the stakeholders.Which of the following is representative of effective communication?a.)Jason contacts the stakeholders before he contacts the project sponsor.b.)It is best for Jason to deliver the bad news through email to avoid confrontation with the stakeholder.c.)Jason emphasizes that the blame is on another team member when he delivers the news.d.)Along with the bad news, Jason should make some recommendations on how to resolve the issue.
Solution
d.) Along with the bad news, Jason should make some recommendations on how to resolve the issue.
Similar Questions
Which of the following should a project manager do to deliver bad news? Provide the name of the individual at fault to document the problemWait to see if the problem will resolve itself before approaching anyoneSend it in an email so that the news is received quicklyInclude the next steps to be used to resolve the issues
Which of the following assists a project manager in communicating in a concise manner with stakeholders? Know the audience and its information needsKnow when the audience is available to communicateKnow the need to use text during presentationsKnow which documents to provide after a meeting
Question 5As a project manager, what should you consider before writing an email to a stakeholder to communicate an issue? Select all that apply.1 pointHow the project will affect you and the stakeholdersHow the problem will affect the company as a wholeWhat is most important to a stakeholderWhat is most important to the project team
Imagine that a restaurant is hosting a recruitment day to hire delivery drivers. The project manager creates a plan to organize stakeholder communication. The plan indicates the following:The team lead updates the core hiring team every day for two weeks prior to the event to report next steps so they each know their daily responsibilities.The core hiring team contacts the job candidates the Friday before the event to remind them of the time and location.The project manager contacts the venue and caterers the Monday before the event to confirm reservations. In the above scenario, what three key elements are missing from the communication plan?1 pointType of communicationResource linksCommunication risksDependenciesDelivery methods
How should a project team communicate? 1 pointThe project team should communicate regularly and in various ways.The project team should use one mode of communication and rely on it consistently.The project team should switch communication tools frequently to increase engagement.The project team should stick to email communication since it is standard practice in business.
Upgrade your grade with Knowee
Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.