A critical chain in a project is constrained by ___Multiple choice question.resource dependenciestechnical dependenciesboth resource and technical dependenciesbudget and schedule dependencies

Question

A critical chain in a project is constrained by ___Multiple choice question.resource dependenciestechnical dependenciesboth resource and technical dependenciesbudget and schedule dependencies

🧐 Not the exact question you are looking for?Go ask a question

Solution

The correct answer is "both resource and technical dependencies".

The critical chain in a project is constrained by both resource and technical dependencies. Resource dependencies refer to the need for specific resources in order for tasks to be completed, such as personnel, equipment, or materials. Technical dependencies refer to the need for certain tasks to be completed before others can begin, based on the technical requirements of the project. Therefore, both types of dependencies can constrain the critical chain in a project.

This problem has been solved

Similar Questions

Multiple Choice QuestionIt is always better to ______________ rather than ______________ dependencies.Multiple choice question.overestimate - underestimateunderestimate - overestimatework on project tasks - map

Multiple Choice QuestionWe cannot factor in resource availability along with technical dependency when creating the original network because even if resources are known, one could not assess the impact of resources unless a Blank______ were created.Multiple choice question.responsibility chartresource neutral scheduledata diagramlist of m

Multiple Choice QuestionWhich statement best describes why resources need to be incorporated into a project precedence network plan?Multiple choice question.Inclusion of resources will allow work packages to be accurately estimated.Project network times cannot become a schedule until resources have been assigned.The inclusion of resources into a project network allows for project priorities to be established.

Which of these is not one of the constraints of a project? Select one: a. Resources b. Budget c. Scope d. Team

Multiple Choice QuestionWhy can the traditional critical path, which is based upon precedence logic, be rendered meaningless after resource constrained leveling is used?Multiple choice question.Leveling will impact activity duration as well as sequence.It can't, the critical path is the critical path by definition.Resource availability becomes an over-riding factor to technical precedence.