Knowee
Questions
Features
Study Tools

The following company information is available for March. The direct materials price variance is: Direct materials purchased and used 4,700 feet @ $99 per footStandard costs for direct materials for March production 4,800 feet @ $97 per foot

Question

The following company information is available for March. The direct materials price variance is: Direct materials purchased and used 4,700 feet @ 99perfootStandardcostsfordirectmaterialsforMarchproduction4,800feet@99 per footStandard costs for direct materials for March production 4,800 feet @ 97 per foot

🧐 Not the exact question you are looking for?Go ask a question

Solution 1

To calculate the direct materials price variance, we need to follow these steps:

  1. First, calculate the actual cost of the materials. This is done by multiplying the actual quantity of materials purchased and used by the actual price per unit. In this case, it would be 4,700 feet * 99/foot=99/foot = 465,300.

  2. Next, calculate the standard cost of the materials. This is done by multiplying the standard quantity of materials by the standard price per unit. In this case, it would be 4,800 feet * 97/foot=97/foot = 465,600.

  3. Finally, subtract the standard cost from the actual cost to find the variance. In this case, it would be 465,300465,300 - 465,600 = -$300.

So, the direct materials price variance is -300.Thismeansthattheactualcostwas300. This means that the actual cost was 300 less than the standard cost.

This problem has been solved

Solution 2

To calculate the direct materials price variance, we need to follow these steps:

  1. First, calculate the actual cost of the materials. This is done by multiplying the actual quantity of materials used by the actual price per unit. In this case, 4,700 feet were used at 99perfoot,sotheactualcostis4,70099 per foot, so the actual cost is 4,700 * 99 = $465,300.

  2. Next, calculate the standard cost of the materials. This is done by multiplying the standard quantity by the standard price per unit. In this case, the standard quantity is 4,800 feet at 97perfoot,sothestandardcostis4,80097 per foot, so the standard cost is 4,800 * 97 = $465,600.

  3. Finally, subtract the standard cost from the actual cost to find the direct materials price variance. In this case, the variance is 465,300465,300 - 465,600 = -$300.

So, the direct materials price variance is -$300. This negative variance indicates that the actual cost was less than the standard cost, which is favorable from a cost control perspective.

This problem has been solved

Similar Questions

The following company information is available. The direct materials quantity variance is: Direct materials used for production 47,000 gallonsStandard quantity for units produced 45,400 gallonsStandard cost per gallon of direct material $ 10.00  Actual cost per gallon of direct material $ 10.20

Parallel Enterprises has collected the following data on one of its products. During the period the company produced 25,000 units. The direct materials price variance is: Direct materials standard (7 pounds @ $2.35/pound) $ 16.45 per finished unitActual cost of materials purchased $ 392,150  Actual direct materials purchased and used 157,000 pounds

Fill in the Blank QuestionFill in the blank question.A company sells a product for $3. Direct materials are $1.80 per unit. The company prepares a flexible budget at two sales volumes. At a sales volume of 50 units, budgeted direct materials will be $. At a sales volume of 60 units, budgeted direct materials will be $.

The standard price of materials is $3.50 per pound and the standard quantity allowed for actual output is 7,000 pounds. If the actual quantity purchased and used was 6,700 pounds, and the actual price per pound was $3.40, the direct materials price variance is

ABC Company has set the following standards for one unit of product: Direct materials: 0.5 pounds @ $1.00 per pound; Direct labor: 1 hour @ $10.00 per hour. The company produced 35,000 units and had the following actual costs: Direct materials: 18,000 pounds at a total cost of $17,280; Direct labor: 36,000 hours at a total cost of $374,400. Compute the direct materials price variance.Multiple choice question.$500 U$720 F$720 U$500 F

1/3

Upgrade your grade with Knowee

Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.