Knowee
Questions
Features
Study Tools

Which activity type is used when work needs to be accomplished in a given time, regardless of the assigned resources’ availability?Level of effortWBS SummaryTask dependentResource dependent

Question

Which activity type is used when work needs to be accomplished in a given time, regardless of the assigned resources’ availability?Level of effortWBS SummaryTask dependentResource dependent

🧐 Not the exact question you are looking for?Go ask a question

Solution

Para responder a esta pregunta, sigamos los siguientes pasos:

  1. Entender las opciones:

    • Level of effort: Este tipo de actividad se refiere a tareas que requieren un esfuerzo constante a lo largo del tiempo, como la supervisión o el mantenimiento.
    • WBS Summary: Este no es un tipo de actividad, sino un resumen del Work Breakdown Structure (Estructura de Desglose del Trabajo).
    • Task dependent: Este tipo de actividad depende de la duración de la tarea en sí misma, sin importar los recursos asignados.
    • Resource dependent: Este tipo de actividad depende de la disponibilidad de los recursos asignados.
  2. Identificar la clave de la pregunta:

    • La pregunta menciona que el trabajo debe ser realizado en un tiempo determinado, independientemente de la disponibilidad de los recursos asignados.
  3. Analizar las opciones en función de la clave:

    • Level of effort: No se ajusta, ya que se refiere a un esfuerzo constante y no a un tiempo específico.
    • WBS Summary: No es relevante, ya que no es un tipo de actividad.
    • Task dependent: Se ajusta, ya que la duración de la tarea es lo importante, no la disponibilidad de los recursos.
    • Resource dependent: No se ajusta, ya que depende de la disponibilidad de los recursos.
  4. Conclusión:

    • La opción correcta es Task dependent, ya que este tipo de actividad se enfoca en la duración de la tarea sin considerar la disponibilidad de los recursos asignados.

Por lo tanto, la respuesta correcta es Task dependent.

This problem has been solved

Similar Questions

Which is an example of Units/Time?Two resources are assigned to an activityResource earns $20/hourResources can work on weekendsResource works 8 hours/day

Which of the following two relate only to the ‘Task’:Space available & duration of the taskWorker’s experience and equipment requiredHow long (duration) & rest periodsPosture required & weight of the load

Which of the following represent individual tasks or activities in the project.a.Slackb.Nodesc.Critical Pathd.Duration

Which of the following is the longest string of dependent project activities required to complete a project in the shortest amount of time? Effort estimateProject scheduleResource estimateCritical path

The Terminology activity is defined as:Question 18Answera.A specific task or set of tasks that are required by the project, use up resources, and take time to completeb.Used deterministic time estimates and allowed project crunchingc.The result of completing one or more activitiesd.The combination of all activities and events that define a project

1/3

Upgrade your grade with Knowee