QuestionA large risk to a project is identified, and the risk management plan is executed. Upon completion of the approved actions, what should the project manager do?A.Update the risk management plan.B.Revise the project schedule and the budget.C.Update the lessons learned.D.Identify new risks, and monitor residual risks.
Question
QuestionA large risk to a project is identified, and the risk management plan is executed. Upon completion of the approved actions, what should the project manager do?A.Update the risk management plan.B.Revise the project schedule and the budget.C.Update the lessons learned.D.Identify new risks, and monitor residual risks.
Solution
The project manager should D. Identify new risks, and monitor residual risks. After executing the risk management plan, it's important to reassess the project landscape for any new potential risks that may have arisen. Additionally, any residual risks - those that remain after risk response planning - should be monitored to ensure they don't escalate.
Similar Questions
As a project manager you are practicing risk management. You have already defined potential risks, determined their likelihood, and prioritized them. Now, you’re making a plan to address and manage each risk. This represents which risk management step?1 pointAnalyze risksTreat risksMonitor and control risksIdentify risks
Risk Management entails all the processes involved in identifying, assessing, analyzing, responding and controlling project risk.Question 1Answera.yesb.agreec.nod.disagree
When is risk management undertaken? Group of answer choicesThroughout the entire life of any project.Only if the project is large and high risk.Only at the start of the project.Only at the end of the project.
Which of the following is true regarding risk management? All risks must have a contingency plan.Risks are more likely to impact the schedule than the budget.Risk identification only occurs in the planning phase of the project.Risks should be reviewed at every team meeting.
What step should you take after you complete your risk management plan?1 pointImplement the individual mitigation plans for the risks you have identified.Estimate the likelihood and impact of the project risks you have prioritized.Share the plan with your team and stakeholders.Create a power grid to include in the appendix of your plan.
Upgrade your grade with Knowee
Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.