James manages a project to build a new pavilion at an elementary school. The concrete floor takes three hours to pour, and three days to set.Which of the following best describes the time between when the concrete is poured, and when the floor is done?Overall timeDependent timeLag timeLead time
Question
James manages a project to build a new pavilion at an elementary school. The concrete floor takes three hours to pour, and three days to set.Which of the following best describes the time between when the concrete is poured, and when the floor is done?Overall timeDependent timeLag timeLead time
Solution
The time between when the concrete is poured, and when the floor is done is best described as Lag time. This is because lag time refers to the delay between tasks that are dependent on each other, in this case, the pouring of the concrete and the setting of the floor.
Similar Questions
Which of the following is the total time it takes to complete a project from start to finish?1 pointDurationMilestoneIssueTask
What is the approximate time difference between a HW and the immediate LW?Group of answer choices12 hr 50 min24 hr 50 min6 hr 12.5 min6 hr 50 min12 hr 25 min
A can do a piece of work in 8 hours. B can do same piece of work in 12 hours. A starts working at 9AM and they worked on alternative hours. At which time work will be finished?
he minimum time required to complete the taskThe maximum time required to complete the taskThe most likely time required to complete the taskThe earliest possible start time for the task
Three machines, X, Y, and Z, can complete a task in 8 hours, 10 hours, and 12 hours, respectively. If they start working one after the other (X, then Y, then Z), how long will it take to complete the task?(APPROX)