The Developers are working on a project that has the Sprint length of three weeks. One week before the end of the Sprint, the Developers estimated that they are able to complete the selected Product Backlog Items three days before the end of the Sprint. What should they do next? (choose the BEST answer) Question 10 options: As all of the planned work for the Sprint has been completed, the Developers can start the Sprint Retrospective ahead of time and work on the improvements for processes, interactions and tools As all of the planned work for the Sprint has been completed, the Developers can work on reducing the technical debt for the Product that is not in listed in the Product Backlog to proactively increase the productivity As all of the planned work for the Sprint has been completed, the Developers can discuss with the Product Owner to select additional Product Backlog Items to work on as long as the Sprint Goal is not affected As Sprint length has a timebox duration of 1 month, the Scrum Team can end the Sprint earlier and proceed to the next Sprint to increase the productivity

Question

The Developers are working on a project that has the Sprint length of three weeks. One week before the end of the Sprint, the Developers estimated that they are able to complete the selected Product Backlog Items three days before the end of the Sprint. What should they do next?

(choose the BEST answer)

Question 10 options:

As all of the planned work for the Sprint has been completed, the Developers can start the Sprint Retrospective ahead of time and work on the improvements for processes, interactions and tools

As all of the planned work for the Sprint has been completed, the Developers can work on reducing the technical debt for the Product that is not in listed in the Product Backlog to proactively increase the productivity

As all of the planned work for the Sprint has been completed, the Developers can discuss with the Product Owner to select additional Product Backlog Items to work on as long as the Sprint Goal is not affected

As Sprint length has a timebox duration of 1 month, the Scrum Team can end the Sprint earlier and proceed to the next Sprint to increase the productivity

...expand
🧐 Not the exact question you are looking for?Go ask a question

Solution

The best answer would be: "As all of the planned work for the Sprint has been completed, the Developers can discuss with the Product Owner to select additional Product Backlog Items to work on as long as the Sprint Goal is not affected"

This is because in Scrum, if the team finishes the work early, they should use the remaining time to pull in more work from the backlog, as long as it doesn't jeopardize the sprint goal. This ensures that the team is always delivering as much value as possible. The other options either involve ending the sprint early, which is not recommended in Scrum, or working on tasks that are not part of the backlog, which could lead to scope creep.

This problem has been solved

Similar Questions

There’s a problem! The end of the sprint is nearing and the development team won’t be able to complete all the stories they originally committed to completing. How can they proceed?Question 8Select one:a.Redefine the definition of done (DoD)b.Enquire with the product owner about what to delay until the next sprintc.Work overtime to complete all storiesd.Bring on additional team members and resources to finish

Question 4Every sprint should have _____.1 pointseveral iterations through the design, code, test, and deploy cyclecompletion of all items in the backloga three-week durationa clearly stated goal

What must the team discuss in sprint planning?When and how they will delver backlog itemsWhether this or an alternative project will deliver more business valueWho will be the Scrum MasterWho on the development team will be on call during the weekends

A Development Team selects a set of Product Backlog items for a Sprint Backlog with the intent to get the selected items "Done" by the end of the Sprint. Which three phrases best describe the purpose of a definition of "Done"?(choose the best three answers)It controls whether the developers have performed their tasks.It defines what it takes for an Increment to be ready for release. It creates transparency over the work inspected at the Sprint Review.It tracks the percentage complete of a Product Backlog item.It provides a template for elements that need to be included in the technical documentation.It guides the Development Team in creating a forecast at the Sprint Planning.

In the upper right-hand corner of your scrum board, you see text that reads “3 days remaining.”What does this indicate?The next sprint starts in three days.The current sprint ends in three days.There are three days until the fix version is released.All items on the board have a due date within the next three days.

1/3

Upgrade your grade with Knowee

Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.