Multiple Choice QuestionXYZ Company makes one product and has calculated the following amounts for direct labor: AH x AR = $84,000; AH x SR = $83,000; SH x SR = $85,000. Compute the direct labor cost variance.Multiple choice question.$2,000 F$2,000 U$1,000 U$1,000 F
Question
Multiple Choice QuestionXYZ Company makes one product and has calculated the following amounts for direct labor: AH x AR = 83,000; SH x SR = 2,000 F1,000 U$1,000 F
Solution
The direct labor cost variance is calculated as the difference between the actual cost of labor and the standard cost of labor.
Here are the given values:
- Actual Hours (AH) x Actual Rate (AR) = $84,000 (Actual Cost)
- Actual Hours (AH) x Standard Rate (SR) = $83,000 (Actual Hours at Standard Rate)
- Standard Hours (SH) x Standard Rate (SR) = $85,000 (Standard Cost)
The formula for direct labor cost variance is:
Direct Labor Cost Variance = Actual Cost - Standard Cost
Substituting the given values into the formula:
Direct Labor Cost Variance = 85,000 = -$1,000
The negative sign indicates that the variance is unfavorable (U), so the answer is $1,000 U.
Similar Questions
Multiple Choice QuestionABC Company has set the following standards for one unit of product: Direct materials: 0.5 pounds @ $1.00 per pound; Direct labor: 1 hour @ $10.00 per hour. The company produced 35,000 units and had the following actual costs: Direct materials: 18,000 pounds at a total cost of $17,280; Direct labor: 36,000 hours at a total cost of $374,400. Compute the direct labor rate variance.Multiple choice question.$10,000 F$14,400 U$10,000 U$14,400 F
Multiple Choice QuestionXYZ Company makes one product and has calculated the following amounts for direct materials: AQ x AP = $150,000; AQ x SP = $145,000; SQ x SP = $152,000. Compute the direct materials price variance.Multiple choice question.$5,000 U$7,000 F$5,000 F$7,000 U
Given the following information, calculate the direct labor price variance. Actual production in units17,000Standard labor cost per unit1/2 hour @ $20 per hourActual cost for labor$216,750 for 12,750 hoursMultiple choice question.$72,750 favorable$38,250 unfavorable$38,250 favorable$72,750 unfavorable
XYZ Company makes one product and has calculated the following amounts for direct materials: Actual cost: AQ x AP = $150,000; AQ x SP = $145,000; Standard cost: SQ x SP = $152,000. Compute the direct materials variance.Multiple choice question.
A planning budget called for 500 units to be produced and total direct labor cost of $7,500. Actual production was 600 units and actual direct labor cost was $9,300. The spending variance is Blank______.Multiple choice question.$300 F$1,800 U$300 U$1,500 F$1,500 U
Upgrade your grade with Knowee