Represents the amount of time an activity can be delayed without impacting the critical path or project completion.a.Slackb.Nodesc.Activitiesd.Duration

Question

Represents the amount of time an activity can be delayed without impacting the critical path or project completion.a.Slackb.Nodesc.Activitiesd.Duration

🧐 Not the exact question you are looking for?Go ask a question

Solution

The correct answer is a. Slack. Slack time is the total time that you can delay a task without delaying the project. More slack time means that project scheduling is more flexible.

Similar Questions

Which of the following represent individual tasks or activities in the project.a.Slackb.Nodesc.Critical Pathd.Duration

Slack= latest finish time minus?a.Earliest finish timeb.Newest finish timec.Average finish timed.Project duration

In a CPM analysis, the activity's slack time can be determined by subtracting the early start from the early finish.Group of answer choicesTrueFalse

Which path duration is considered as the project completion timea.Shortest pathb.Longest Pathc.Most likely pathd.None of the given options

___________ shows which of the activities can be delayed along with its interdependences.Question 20Answera.Communication chartb.Network Schedulingc.Work package leveld.Flow chart