A can do a piece of work in 25 days and B can do the same work in 30 days. They work together for 5 days, how much of work is left?Options1126319/301129315/30

Question

A can do a piece of work in 25 days and B can do the same work in 30 days. They work together for 5 days, how much of work is left?Options1126319/301129315/30

🧐 Not the exact question you are looking for?Go ask a question

Solution 1

Sure, let's solve this step by step:

  1. First, we need to find out how much work A and B can do in a day.

    A can finish the work in 25 days, so A can do 1/25 of the work in a day.

    B can finish the work in 30 days, so B can do 1/30 of the work in a day.

  2. Now, let's find out how much work they can do together in a day.

    A and B together can do (1/25 + 1/30) of the work in a day.

    To add these two fractions, we need to find a common denominator. The least common multiple of 25 and 30 is 150. So, we convert the fractions to have the denominator 150:

    A's work = (1/25) * 6/6 = 6/150

    B's work = (1/30) * 5/5 = 5/150

    Adding these two, A and B together can do (6/150 + 5/150) = 11/150 of the work in a day.

  3. They work together for 5 days, so in 5 days, they can do 5 * (11/150) = 55/150 of the work.

  4. To find out how much of the work is left, we subtract the work done from the total work (which is 1).

    So, the work left is 1 - 55/150 = 95/150 = 19/30 of the work.

So, the correct option is 19/30.

This problem has been solved

Solution 2

Sure, let's solve this step by step:

  1. First, we need to find out how much work A and B can do in one day.

    A can finish the work in 25 days, so A can do 1/25 of the work in one day.

    B can finish the work in 30 days, so B can do 1/30 of the work in one day.

  2. Now, let's find out how much work they can do together in one day.

    If we add the work A and B can do, we get: 1/25 + 1/30 = 6/150 + 5/150 = 11/150.

    So, together they can do 11/150 of the work in one day.

  3. They work together for 5 days, so the amount of work they can do in 5 days is:

    5 * 11/150 = 55/150 = 11/30 of the work.

  4. Since the total work to be done is 1 (or 30/30), the amount of work left after they work for 5 days is:

    1 - 11/30 = 19/30 of the work.

So, the amount of work left is 19/30. Therefore, the correct option is 19/30.

This problem has been solved

Similar Questions

A can do a work in 36 days and B in 32 days. If they work on it together for 12 days, then what fraction of work is left?Options7/2411933134557/72

A, B and C can do a work in 20 days, 24 days and 30 days respectively. A and B left the work 4 days before completion of the work, then whole work will finish in how many days?Options10 14/1511 8/159 2/312 7/15

A can do a work in 15 days and B in 20 days. If they work on it together for 4 days, then the fraction of the work that is left is :

A can do a piece of work in 5 days and B in 20 days. They work together for 2 days and then both leave the work. Then C alone can finish the remaining work in 6 days. In how many days will C finish the full work?

Select the correct answerA, B and C can do a piece of work in 30 days, 45 days and 90 days, respectively. A starts the work and he is assisted by B and C together on every third day. In how many days will the work be completed?Options24233022