What two questions can a project manager ask to determine a project’s costs? Select all that apply.1 pointHow much time will people have to spend on the project?What are the ongoing project costs?How will the user experience be improved?What value will the project create?
Question
What two questions can a project manager ask to determine a project’s costs? Select all that apply.1 pointHow much time will people have to spend on the project?What are the ongoing project costs?How will the user experience be improved?What value will the project create?
Solution
The two questions a project manager can ask to determine a project’s costs are:
- How much time will people have to spend on the project?
- What are the ongoing project costs?
These two questions directly relate to the financial aspect of the project. The first question helps to estimate labor costs, while the second question helps to identify any recurring costs that will be incurred throughout the project's lifecycle.
Similar Questions
David is leading a software development project for his company. He is in the process of budgeting and needs to distinguish between real project costs and overhead costs. Which item would be considered a real project cost for David's project?David's computerThe salary of the software developers hired for David's projectThe annual licensing fee for David's project management softwareThe rent for the office space where David works
Questions such as 'How will the project plan be developed?' and 'What are the specific roles and responsibilities of the participants?' are part of the ____ decisions a project manager needs to address.Multiple choice question.trackingplanningrelationship
Question 8Your manager assigns you a project task, and you don’t understand the point of the project. What questions can you ask them to determine the objective? Select all that apply.1 pointWhat is the story they want to tell?What is their end goal?What do you have to do for this task?What is the big picture?
Question 3As a project manager, the project sponsor gives you cost estimates with a set amount of money to spend. What challenge for effective budgeting does this represent?1 pointInsufficient cash flowLack of historical dataPre-allocated budgetScope creep
Multiple Choice QuestionIn project monitoring information systems, ___ determine(s) what data to collect.Multiple choice question.the baseline project budgetthe metrics used for project controlthe baseline project schedule