As the project manager you are reviewing the earned value analysis report performed by your team. The SPI is 0.87. What does this figure mean to you?Your project is running according to the budget.The project is getting 87 cents out of each dollar spent.You are ahead of schedule.The progress of your project is only 87% of what it is planned, so you are behind the schedule.

Question

As the project manager you are reviewing the earned value analysis report performed by your team. The SPI is 0.87. What does this figure mean to you?Your project is running according to the budget.The project is getting 87 cents out of each dollar spent.You are ahead of schedule.The progress of your project is only 87% of what it is planned, so you are behind the schedule.

🧐 Not the exact question you are looking for?Go ask a question

Solution

The SPI (Schedule Performance Index) is a measure of the efficiency of time utilization on the project. If the SPI is less than 1, as in this case where it is 0.87, it means the project is behind schedule. In other words, the progress of your project is only 87% of what it was planned. Therefore, you need to take action to bring the project back on track.

Similar Questions

What is the best explanation for "an SPI of 0.80"?Multiple choice question.$1.00 of work has been accomplished for each $0.80 of work scheduled to date.$0.80 of work has been accomplished for each $1.00 of work scheduled to date.$0.80 has been spent for each $1.00 of work planned to be accomplished.

SPI = 0.95,CPI = 0.95 Which of the following statements is true?2 MarksThe project will likely complete within timeThe project will likely be completed under budgetThe project manager should remove some scope from the projectThe project manager needs to improve schedule and cost performance

What is the meaning of an index of "=1.00" on SPI?Multiple choice question.Under costOn costOver costAhead of scheduleOn scheduleBehind schedule

projectA initial cost 12000, scape value is 10% of initial cost, what is the projectA annual depreciation

Which value for TCPI indicates the project is under budget?Multiple choice question.0.781.001.78

1/1