A new project you are reviewing will generate an operating cash flow of $19,000. The project will free up $3,500 in net working capital. Initially, $4,500 will be needed for fixed asset purchases. What is the total cash flow for this project at time zero? Group of answer choices $18,000 $20,000 -$1,000 $1,000 $8,000

Question

A new project you are reviewing will generate an operating cash flow of 19,000.Theprojectwillfreeup19,000. The project will free up 3,500 in net working capital. Initially, $4,500 will be needed for fixed asset purchases. What is the total cash flow for this project at time zero?

Group of answer choices

$18,000

$20,000

-$1,000

$1,000

$8,000

🧐 Not the exact question you are looking for?Go ask a question

Solution

The total cash flow for a project at time zero can be calculated by adding the operating cash flow, the net working capital, and the fixed asset purchases (which is usually considered as a cash outflow, hence it is subtracted).

Here's how you can calculate:

Operating Cash Flow: 19,000NetWorkingCapital:19,000 Net Working Capital: 3,500 Fixed Asset Purchases: $4,500

Total Cash Flow at Time Zero = Operating Cash Flow + Net Working Capital - Fixed Asset Purchases

Total Cash Flow at Time Zero = 19,000+19,000 + 3,500 - 4,500=4,500 = 18,000

So, the total cash flow for this project at time zero is $18,000.

This problem has been solved

Similar Questions

Using the method of your choice, calculate the Net Present Value of the following cash flows. Assume that the required return on this project is 15%  Project AInitial Cost -$ 150  Year 1 $ 175  Year 2 $ 100

What is the incremental cash flow for a company that pays $5000 to a consulting firm to undertake a feasibility study for a project  that will return net cash inflows of $25,000 p.a ?Group of answer choices$25,000$30,000$20,000Not enough information to answer$10,000

Discounted cash flows applicationsNet present Value calculations have a broad range of applications in finance.Calculate the NPV of the project based on the information below.Initial investment: $20,00Cash flow generated each year: $5,000Total period: 5 YearsDiscount rate: 6%

What is the maximum that should be invested in a project at time zero if the inflows are estimated at $25,000 annually for four years, and the cost of capital is 9%?Question 2Select one:a.$19,007.00b.$25,000.00c.$91,743.12d.$80,993.00

Consider a project with free cash flows in one year of $90,000 in a weak economy or $117,000 in a strong economy, with each outcome being equally likely. The initial investment required for the project is $80,000, and the project's cost of capital is 15%. The risk-free interest rate is 5%.The NPV for this project is closest to:Group of answer choices$14,100.$6250.$10,000.$18,600.

1/3

Upgrade your grade with Knowee

Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.