A is thrice as efficient as B and takes 10 days less than B takes to do the same work. In howmany days, B alone can finish the whole work?

Question

A is thrice as efficient as B and takes 10 days less than B takes to do the same work. In howmany days, B alone can finish the whole work?

🧐 Not the exact question you are looking for?Go ask a question

Solution

Let's assume that B takes x days to finish the whole work.

According to the given information, A is thrice as efficient as B. This means that A can finish the same amount of work in one-third of the time taken by B. So, A takes x/3 days to finish the whole work.

It is also given that A takes 10 days less than B to do the same work. This means that A takes x - 10 days to finish the whole work.

Since we know that A takes x/3 days and x - 10 days to finish the whole work, we can set up the equation:

x/3 = x - 10

To solve this equation, we can multiply both sides by 3 to eliminate the fraction:

3(x/3) = 3(x - 10) x = 3x - 30

Next, we can simplify the equation:

2x = 30 x = 15

Therefore, B alone can finish the whole work in 15 days.

This problem has been solved

Similar Questions

A and B working together can complete a work in 10 days. If A works at half of his efficiency and B works at thrice of his efficiency, they can complete the work in 6 days. In how many days can A complete the work at his normal efficiency?

A takes 10 days less than the time taken by B to finish a piece of work. If both A and B can do it in 12 days, then the time taken by B alone to finish the work is?Options30 days20 days25 days27 days

A is twice as fast in work as B is. If B can do a piece of work in 10 days, then A can do the same work in:

when working alone A takes 24 more days than time taken by A and B together to finish certain work. If A is 50% more efficient than B, then find the time taken by B to finish the work alone.

If A is 25% as efficient as B and can complete a certain work taking 15 days more than the time taken by B, in how many days will both A and B together complete the work?4 days5 days7 days10 days

1/3

Upgrade your grade with Knowee

Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.