Question
The time box for the Sprint Planning event is?8 hours for a monthly sprint. For shorter sprints, it is usually shorter4 hoursWhenever it is doneMonthly
Solution
The time box for the Sprint Planning event is 8 hours for a monthly sprint. For shorter sprints, the time box is usually less, often around 4 hours. However, the exact duration can vary and should be determined based on when the planning is considered complete.
Similar Questions
Sprint Retrospective is a Scrum event that has a timebox duration of three hours. (choose the BEST answer) Question 4 options: For a one-week Sprint, Sprint Retrospective's duration can be longer than three hours to get additional valuable feedback from the Scrum Team for future adaptation For a one-month Sprint, Sprint Retrospective's maximum duration is three hours For a one-week Sprint, Sprint Retrospective's maximum duration is three hours This is incorrect. Sprint Retrospective has a timebox duration of four hours For a one-month Sprint, Sprint Retrospective's duration is precisely three hours For a one-month Sprint, Sprint Retrospective's duration can be longer than three hours to get additional valuable feedback from the Scrum Team for future adaptation For a one-week Sprint, Sprint Retrospective's duration is precisely three hours
Question 3How long is a typical Sprint’s timebox?1 pointBetween one and three daysBetween one and four weeksBetween two and three months
How long should sprint planning normally take, if the duration of the Sprint is 2 weeks? 1 hourHalf hour4 hours14 minutes or les
Which of the following factors should you consider when setting the length of a Sprint’s timebox? Select all that apply.1 pointThe likelihood that the project will go over budgetHow much overhead—such as testing and review—goes into the delivery of the productThe expected frequency of changesHow much focused time the solution Developers need to build a Backlog item
ime-boxing is an important principle of Scrum. Identify the incorrect statement.1. A Sprint is time-boxed to 1 to 4 weeks; A Sprint Planning Meeting is time-boxed to 8 hours for a one month Sprint; A Daily Standup is time-boxed to 15 minutes.2. A Daily Standup is time-boxed to 15 minutes; A Sprint Review Meeting is time-boxed to 4 hours for a one month Sprint; A Sprint is time-boxed to 1 to 6 weeks.3. A Sprint Review Meeting is time-boxed to 6 hours for a 4-week Sprint; A Retrospect Sprint Meeting is time-boxed to 8 hours for a 4-week Sprint; A Sprint Planning Meeting is time-boxed to 8 hours for a one week Sprint.4. A Retrospect Sprint Meeting is time-boxed to 4 hours for a one month Sprint; A Daily Standup is time-boxed to 15 minutes; A Sprint is time-boxed to 1 to 6 weeks.