Select the correct statement regarding kanban pipelines. 1 pointThe first pipeline on a kanban board is product backlog. The sprint backlog is followed by the icebox. The new issues pipeline is for storing items you will do in the next two weeks. A kanban board is made of multiple pipelines.

Question

Select the correct statement regarding kanban pipelines. 1 pointThe first pipeline on a kanban board is product backlog. The sprint backlog is followed by the icebox. The new issues pipeline is for storing items you will do in the next two weeks. A kanban board is made of multiple pipelines.

🧐 Not the exact question you are looking for?Go ask a question

Solution

The correct statement regarding kanban pipelines is: "A kanban board is made of multiple pipelines."

Here's why:

  1. The first pipeline on a kanban board is not necessarily the product backlog. It can vary based on the team's workflow. It could be "To Do", "Backlog", or something else.

  2. The sprint backlog is a term used in Scrum, not Kanban. Also, the icebox is typically a place for low-priority or long-term tasks, not something that follows the sprint backlog.

  3. The "New Issues" pipeline is not specifically for storing items you will do in the next two weeks. It's generally for new tasks or issues that have been identified but not yet prioritized or scheduled.

  4. A kanban board is indeed made of multiple pipelines, each representing a different stage in the workflow. This is the correct statement.

This problem has been solved

Similar Questions

As you develop a new product, you frequently need to switch between the Backlog and Kanban board to see various issues.What is the quickest way to do so?through the main navigation barthrough the project sidebarthrough the search barthrough the product switcher

Identify one purpose of a Kanban board.display issues in the current sprintmeasure team velocitysee the timeline for estimated workhelp identify blockers and dependenciesThis item can be moved. Use the space bar to grab it.Next

Question 9What is a kanban board?1 pointA kanban board is made up of multiple project management tools.A type of waterfall chart depicting the phases of the project.A method for tracking planned items and showing progress as items are moved across the board.Colored sticky notes, placed on a board primarily to highlight problem areas.

Question 5What happens to stories put in the icebox on a kanban board?1 pointThey are rejected.They eventually may be moved to the product backlog.They remain in the icebox, like an archived item.They are items that will not go to the backlog.

When a kanban team member is ready to work on a new issue in the standard Jira kanban workflow, which one of the following is usually true?1 pointAny issue from the backlog is pulled to the "in progress" column.A planning meeting should be called.The issue at the top of the "selected for development" column is pulled to the "in progress" column.

1/2

Upgrade your grade with Knowee

Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.