A can do work in 15 days and B in 20 days. If they work on it together for 4 days, then the fraction of the work that is left is:

Question

A can do work in 15 days and B in 20 days. If they work on it together for 4 days, then the fraction of the work that is left is:

🧐 Not the exact question you are looking for?Go ask a question

Solution

Sure, let's solve this step by step:

Step 1: Find out how much work A and B can do in a day. A can finish the work in 15 days, so A can do 1/15 of the work in a day. Similarly, B can finish the work in 20 days, so B can do 1/20 of the work in a day.

Step 2: Find out how much work A and B can do together in a day. If A can do 1/15 of the work in a day and B can do 1/20 of the work in a day, together they can do (1/15 + 1/20) of the work in a day. This equals 7/60 of the work in a day.

Step 3: Find out how much work A and B can do together in 4 days. If they can do 7/60 of the work in a day, in 4 days they can do 4*(7/60) = 7/15 of the work.

Step 4: Find out the fraction of the work that is left. If they have done 7/15 of the work, the fraction of the work that is left is 1 - 7/15 = 8/15.

So, the fraction of the work that is left is 8/15.

This problem has been solved

Similar Questions

A and B can complete a work in 15 days and 10 days respectively. They started doing the work together but after 2 days B had to leave and A alone completed the remaining work. The whole work was completed in :8 days10 days12 days15 days

A can do 2/5 of a work in 12 days while B can do 66 2/3% of the same work in 16 days. They work together for 10 days. B alone will complete the remaining work in?Options6498

If A can do a piece of work in 10 days and B can do the same work in 15 days, how long will they take to complete it together?

A and B can do a piece of work in 45 and 40 days respectively. They began the work together but A left after some days and B finished the remaining work in 23 days. A left after

A can do a work in 36 days and B in 32 days. If they work on it together for 12 days, then what fraction of work is left?Options7/24134557/7211933

1/3