Knowee
Questions
Features
Study Tools

S can do a piece of work in 10 days and T in 30 days. They begin together but S leaves 3 days before the completion of the work. The remaining work will be done in how many days?6. 75 days11. 25 days8. 5 days15.5 day

Question

S can do a piece of work in 10 days and T in 30 days. They begin together but S leaves 3 days before the completion of the work. The remaining work will be done in how many days?6. 75 days11. 25 days8. 5 days15.5 day

🧐 Not the exact question you are looking for?Go ask a question

Solution

First, let's find out how much work S and T can do in a day.

S can complete the work in 10 days, so S can do 1/10 of the work in a day. T can complete the work in 30 days, so T can do 1/30 of the work in a day.

When they work together, they can do (1/10 + 1/30) = 4/30 = 2/15 of the work in a day.

Let's say the total work takes D days. We know that S leaves 3 days before the completion of the work, so S works for (D-3) days.

So, the work done by S is (D-3) * (1/10).

Since T works for all D days, the work done by T is D * (1/30).

The total work done (which is 1, since they complete the work) is the sum of the work done by S and T, so we have the equation:

(D-3) * (1/10) + D * (1/30) = 1

Solving this equation for D gives us D = 11.25 days.

So, the work will be completed in 11.25 days.

However, since S leaves 3 days before the completion of the work, the remaining work after S leaves will be done in 3 days.

This problem has been solved

Similar Questions

A can do a piece of work in 8 days and B can do the same work in 10 days. They started the work together but after 3 days, A left . In how many days B can complete the remaining work?4 days7 days7.5 days3. 25 days

A, B and C can do a piece of work in 20, 30 and 40 days, respectively. A and C started the work and B joined 4 days later. A left 8 days before the completion of work and C was also absent for 5 days in between. How many days will it take for the work to be completed?

A can finish a work in 24 days, B in 9 days and C in 12 days. B & C start the work but are forced to leave after 3 days. The remaining work done by A in:

If A can do a piece of work in 10 days and B can do the same work in 15 days, how long will they take to complete it together?

A and B can complete a work in 15 days and 10 days respectively. They started doing the work together but after 2 days B had to leave and A alone completed the remaining work. The whole work was completed in :8 days10 days12 days15 days

1/3

Upgrade your grade with Knowee

Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.