Multiple Choice QuestionWhich of the following is a goal of smoothing?Multiple choice question.Increase the number of resources used over the life of the project.Increase peak of demand for the resource.Minimize fluctuations in resource demand.

Question

Multiple Choice QuestionWhich of the following is a goal of smoothing?Multiple choice question.Increase the number of resources used over the life of the project.Increase peak of demand for the resource.Minimize fluctuations in resource demand.

🧐 Not the exact question you are looking for?Go ask a question

Solution

The goal of smoothing in project management is to "Minimize fluctuations in resource demand."

Smoothing, also known as 'leveling', is a technique used in project management to ensure a consistent use of resources over time. This is done by redistributing the work evenly to avoid any significant fluctuations in resource demand. This helps in avoiding any periods of high or low demand, ensuring that resources are not overused or underused at any point in time. Therefore, the correct answer is "Minimize fluctuations in resource demand."

This problem has been solved

Similar Questions

Multiple Choice QuestionWhich of the following is true of smoothing/leveling resources in a time-constrained project?Multiple choice question.There are no risks in a time-constrained project.Changing the precedence relationship of activitiesLoss of scheduling flexibility

Multiple Choice QuestionImprovements in the quality of a variable resource increase Blank______ and therefore its demand.Multiple choice question.costsmarginal productivityqualityresource supplymarginal supply

Multiple Choice QuestionWhich of the following increases marginal productivity and therefore its demand?Multiple choice question.Improvements in the quality of a variable resourceImprovements in the quantities of a variable resourceImprovements in the supply of a variable resourceImprovements in the demand of a variable resource

Multiple Choice QuestionThe priority rules for resource smoothing are applied in ___.Multiple choice question.any period when two or more activities require the same resourceany period when a critical path activity is scheduledevery time period of a project

Multiple Select QuestionSelect all that applyWhat can shift the resource demand curve?Multiple select question.Prices of other resourcesProduct demandProduct supplyResource productivity

1/3

Upgrade your grade with Knowee

Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.