What budgeting challenge arises when changes or growth cause additional work the project manager hadn’t planned for?1 pointBudget pre-allocationInaccurately accounting for total costsInaccurate budget baselineScope creep

Question

What budgeting challenge arises when changes or growth cause additional work the project manager hadn’t planned for?1 pointBudget pre-allocationInaccurately accounting for total costsInaccurate budget baselineScope creep

🧐 Not the exact question you are looking for?Go ask a question

Solution

The budgeting challenge that arises when changes or growth cause additional work the project manager hadn’t planned for is known as Scope Creep.

Scope Creep refers to the changes, continuous or uncontrolled growth in a project’s scope, at any point after the project begins. This can occur when the scope of a project is not properly defined, documented, or controlled. It is generally considered harmful and it is advisable to avoid it. If the scope is not actively controlled, then it may lead to extra work, over budget, and delay in project delivery.

This problem has been solved

Similar Questions

Question 3As a project manager, the project sponsor gives you cost estimates with a set amount of money to spend. What challenge for effective budgeting does this represent?1 pointInsufficient cash flowLack of historical dataPre-allocated budgetScope creep

As a project manager setting a budget, you factor in unexpected costs that may arise during the project. What budgeting strategy does this refer to?1 pointSetting a baselineBottom-up approachLeveraging expertsAdding a buffer and reserves

As a project manager, what project component should you focus on to minimize the likelihood of incurring changes to the project budget or extensions in the project timeline?1 pointProposalsRetrospectivesTeam membersScope

As a project manager, you think about where your budget might exceed estimates and how the project might get off track. Which project planning component are you implementing? 1 pointProject budget planProject scheduleRisk management planRisk reviews

Fill in the blank: A project manager needs to alter their budget after making changes to the project schedule and costs. This is necessary in order to _____.1 pointre-baseline the budget to track project progress of costsre-baseline the budget to track project progress of tasksbaseline the budget to track project progress of reservesbaseline the budget to track project progress of costs