A can do a piece of work in 8 days and B can do the same work in 10 days. They started the work together but after 3 days, A left . In how many days B can complete the remaining work?

Question

A can do a piece of work in 8 days and B can do the same work in 10 days. They started the work together but after 3 days, A left . In how many days B can complete the remaining work?

🧐 Not the exact question you are looking for?Go ask a question

Solution

First, let's find out how much work A and B can do in a day.

A can finish the work in 8 days, so A can do 1/8 of the work in a day. B can finish the work in 10 days, so B can do 1/10 of the work in a day.

When they work together, they can do (1/8 + 1/10) of the work in a day. This simplifies to 9/40 of the work in a day.

They worked together for 3 days, so in 3 days, they did 3 * (9/40) = 27/40 of the work.

This means that the remaining work is 1 - 27/40 = 13/40 of the work.

Now, B is left to do the remaining work alone. Since B can do 1/10 of the work in a day, it will take B (13/40) / (1/10) = 13/4 = 3.25 days to finish the remaining work.

So, B can complete the remaining work in 3.25 days.

This problem has been solved

Similar Questions

A and B can complete a work in 15 days and 10 days respectively. They started doing the work together but after 2 days B had to leave and A alone completed the remaining work. The whole work was completed in :8 days10 days12 days15 days

A and B can complete a work in 6 days.A can alone do it in 10 days.Then B can alone do the work in how many days?A13.75 daysB14 daysC16 daysD15 days

A started a work and left working after 9 days now B finished the remaining work in 24 days. Had A left the work after working for 13 days then B would have finished the remaining work in next 18 days. Then find in how many days A and B together can complete the work?Options12 days16 days18 days15 days

If A can do a piece of work in 10 days and B can do the same work in 15 days, how long will they take to complete it together?

S can do a piece of work in 10 days and T in 30 days. They begin together but S leaves 3 days before the completion of the work. The remaining work will be done in how many days?

1/3