Create Network Diagram (2.5pts) A. Use Ms Project to draw a network from the following information. ID Predecessor A None B A C B D B E C F C G D E F H G B. What type of activity is each of the following? Choose one of the following: neither burst nor merge, or burst, or merge. Activity A Activity B Activity C Activity D Activity E Activity F Activity G Activity H
Question
Create Network Diagram (2.5pts) A. Use Ms Project to draw a network from the following information. ID Predecessor A None B A C B D B E C F C G D E F H G B. What type of activity is each of the following? Choose one of the following: neither burst nor merge, or burst, or merge. Activity A Activity B Activity C Activity D Activity E Activity F Activity G Activity H
Solution
A. To create a network diagram in MS Project, follow these steps:
- Open MS Project and create a new project.
- In the "Task Name" field, enter the activities A to H.
- In the "Predecessors" column, enter the predecessor for each task as given in the question. For example, for task B, enter A as the predecessor, for task C, enter B as the predecessor, and so on.
- Once all tasks and their predecessors are entered, go to the "View" tab.
- In the "View" tab, click on "Network Diagram" in the "Task Views" group.
B. The type of activity for each of the following is:
Activity A: Neither burst nor merge (it only has one successor) Activity B: Burst (it has more than one successor) Activity C: Merge (it has more than one predecessor) Activity D: Neither burst nor merge (it only has one successor and one predecessor) Activity E: Merge (it has more than one predecessor) Activity F: Neither burst nor merge (it only has one successor and one predecessor) Activity G: Burst (it has more than one successor) Activity H: Neither burst nor merge (it only has one predecessor)
Similar Questions
Create Network Diagram (2.5pts) A. Use Ms Project to draw a network from the following information. ID Predecessor A None B A C B D B E C F C G D E F H G
In a project, a network diagram shows the ------------ relations of theinter related activities along with their corresponding activity times. deterministic and probabilistic precedence or succession union and intersection dummy and artificial
The sequence of activity in network diagrams is shown by?a.Arrowsb.Nodesc.Circlesd.squares
Once the network diagram is complete, how many activities or milestones will not have both a predecessor and a successor? A. 1 B. 1 in each phase C. As many as necessary D. 2 in the entire network
Which of the following is NOT a valid construct as part of an activity diagram?
Upgrade your grade with Knowee
Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.