B and C together can complete a work in 8 days, A and B together can complete the same work in 12 days, and A and C together can complete the same work in 16 days. In how many days can A, B and C together completes the work?Options3.6923076927.3846153857.4166666673.416666667

Question

B and C together can complete a work in 8 days, A and B together can complete the same work in 12 days, and A and C together can complete the same work in 16 days. In how many days can A, B and C together completes the work?Options3.6923076927.3846153857.4166666673.416666667

🧐 Not the exact question you are looking for?Go ask a question

Solution

The problem can be solved using the concept of work and time.

Step 1: Find the work done by A, B, and C in one day.

We know that B and C can complete the work in 8 days, so the work done by B and C in one day is 1/8.

Similarly, the work done by A and B in one day is 1/12, and the work done by A and C in one day is 1/16.

Step 2: Add the work done by the pairs in one day.

(Work done by B and C) + (Work done by A and B) + (Work done by A and C) = (1/8) + (1/12) + (1/16) = 1/4

Step 3: Divide the total work done by the pairs in one day by 2 to get the work done by A, B, and C in one day.

(Work done by A, B, and C in one day) = (1/4) / 2 = 1/8

Step 4: The time taken by A, B, and C to complete the work is the reciprocal of the work done by them in one day.

So, the time taken by A, B, and C to complete the work = 1 / (1/8) = 8 days

Therefore, A, B, and C together can complete the work in 8 days.

This problem has been solved

Similar Questions

Select the correct answerA and B together can do a piece of work in 12 days which B and C together do in 16 days. If A works for 5 days, B works for 7 days than C completes the remaining work in 13 days. In how much time B alone does the whole work?Options48 days16 days24 days12 days

A, B and C can do a work separately in 24, 36 and 48 days respectively. B leaves 7 days before completion and A left 3 days before completion. work will finish in how many days?Options11 5/1312 7/1314 8/1313 9/13

A and B can do a work in 12 days and 18 days, respectively. They worked together for 4 days after which B was replaced by C and the remaining work was completed by A and C in the next 4 days. In how many days will C alone complete 50% of the same work?

A and B can separately do a work in 12 days & 24 days . They worked together for 6 days after which B was replaced by C . If the work was finished in next 9/4 days, the number of days in which C alone could do the work?

A alone can complete a work in 16 days and B alone in 12 days. Starting with A, they work on alternate days. The total work will be completed in ______.A 12 days B 13 days C  days D  days

1/3

Upgrade your grade with Knowee

Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.