A manufacturing company has a small productionline dedicated to the production of a particularproduct. The line has four stations in serial. Inputsarrive at station 1 and the output from station 1becomes the input to station 2. The output fromstation 2 is the input to station 3 and so on. Theoutput from station 4 is the finished product. Station1 can process 2,700 units per month, station 2 canprocess 2,500/month, station 3 can process2,300/month, and station 4 2,100/month. Whatstation sets the maximum possible output from thissystem? What is that maximum output number?

Question

A manufacturing company has a small productionline dedicated to the production of a particularproduct. The line has four stations in serial. Inputsarrive at station 1 and the output from station 1becomes the input to station 2. The output fromstation 2 is the input to station 3 and so on. Theoutput from station 4 is the finished product. Station1 can process 2,700 units per month, station 2 canprocess 2,500/month, station 3 can process2,300/month, and station 4 2,100/month. Whatstation sets the maximum possible output from thissystem? What is that maximum output number?

...expand
🧐 Not the exact question you are looking for?Go ask a question

Solution

The maximum possible output from this system is set by the station with the lowest processing capacity, as it would be the bottleneck in the production line. In this case, that would be station 4, which can process 2,100 units per month. Therefore, the maximum output number from this system would be 2,100 units per month.

Similar Questions

A plant manager is attempting to determine the production schedule of various products to maximize profit. Assume that a machine hour constraint is binding. If the original amount of machine hours available is 200 minutes, and the range of feasibility is from 130 minutes to 300 minutes, providing two additional machine hours will result in:Group of answer choicesthe same product mix, same total profit.a different product mix, different total profit.the same product mix, different total profit.a different product mix, same total profit as before.

A factory can produce two products, x and y, with a profit P approximated by P = 12x + 15y. The production of y can exceed x by no more than 200 units.  Moreover, production levels are limited by the formula x + 2y ≤ 1000. What production levels yield maximum profit?

A manufacturer produces two products A and B that are processed on two machines I and II before completion. Machine I can process either 25 units of product A or 10 units of product B per hour. Machine II can process 40 of product B or 20 units of product A per hour.Using matrices determine the following:(i) Monthly output of products A and B if machines I and II operate for 8 and 7 hours per day respectively in a 6-day working week with 4 weeks in a month.mission0000(ii) Per unit cost of production if the cost of operating per hour on two machines is 25,000 and 30,000 respectively.(iii) Total cost of production.

A company has three machines and each can produce 200,000 products per year. Each machine requires two operators. The forecast demand for next year is 150, 000 products. What would be the machine requirement for the next year?Group of answer choices0.501.500.750.252.25

A can lay railway track between two given stations in 16 days and B can do the same job in 12 days. With help of C, they did the job in 4 days only. Then, C alone can do the job in