A and B complete a work in 6 days. A alone can do it in 10 days. If both together can do the work in how many days?a. 6 daysb. 4 daysc. 5 daysd. 3.75 days

Question

A and B complete a work in 6 days. A alone can do it in 10 days. If both together can do the work in how many days?a. 6 daysb. 4 daysc. 5 daysd. 3.75 days

🧐 Not the exact question you are looking for?Go ask a question

Solution

The question seems to have a mistake. It says "A and B complete a work in 6 days. A alone can do it in 10 days. If both together can do the work in how many days?" But it has already mentioned that A and B together can complete the work in 6 days. So, the answer should be 6 days (option a).

Similar Questions

Select the correct answerA and B together can finish a work in 6.75 days. A alone can finish the same work in 9 days. In how many days will B alone finish the work?Options27 days18 days35 days36 days

A can do a piece of work in 8 days and B can do the same work in 10 days. They started the work together but after 3 days, A left . In how many days B can complete the remaining work?4 days7 days7.5 days3. 25 days

A and B can do a piece of work in 6 2/3 days and 5 days respectively. They work together for 2 days and then A leaves. In how many days after that B will complete the work alone.a.3 ½ daysb.2 daysc.1 ½ daysd.3 days

A and B together can do a specific work in 8 days. B alone can do it in 10 days, then time taken by A alone is

A and B working together can complete a work in 10 days. If A works at half of his efficiency and B works at thrice of his efficiency, they can complete the work in 6 days. In how many days can A complete the work at his normal efficiency?

1/3