Fill in the missing word: Time, cost and … is the essence in the execution of a projecta.communicationb.qualityc.controld.reports
Question
Fill in the missing word: Time, cost and … is the essence in the execution of a projecta.communicationb.qualityc.controld.reports
Solution
The missing word in the sentence "Time, cost and … is the essence in the execution of a project" is quality. So, the correct option is b. quality.
Similar Questions
Project Management Triangle consist ofa.Time, money, qualityb.Quality, Cost, Deliveryc.Scope, Time, Qualityd.Cost, Scope, Time
__________consists of those processes performed to observe project execution so that potential problems can be identified in a timely manner and corrective action can be takenQuestion 8Answera.Planningb.Procurementc.Monitoring and Controllingd.Quality Assurance
Fill in the missing word: … is the first phase of managing your project.a.Controllingb.Communicatingc.Planningd.Reporting
The cost baseline is developed during which process?Develop scheduleDetermine budgetEstimate costsMonitor & control project work
Which of the following must be done by project team members to assist the project manager in monitoring a project budget? Report the impact of completing a deliverableRecord effort continuously during the completion of a taskRecord the risks associated with the project tasksReport services provided by a vendor with a fixed bid contract