What is a particular task/exercise in a project known as CPM?a.Activityb.Eventc.Taild.Head
Question
What is a particular task/exercise in a project known as CPM?a.Activityb.Eventc.Taild.Head
Solution
The answer is a. Activity. In a project known as CPM (Critical Path Method), a particular task or exercise is referred to as an Activity.
Similar Questions
CPM help in Early identification of ________ activitiesa.Criticalb.Non- Criticalc.Regulard.Non- Regular
Which of the following brings together a set of tools and techniques used to describe, organise and monitor the work of project activities?Group of answer choicesProject ManagementStakeholdersProject ManagersA Guide to PMBOK
The Terminology activity is defined as:Question 18Answera.A specific task or set of tasks that are required by the project, use up resources, and take time to completeb.Used deterministic time estimates and allowed project crunchingc.The result of completing one or more activitiesd.The combination of all activities and events that define a project
Which of the following represent individual tasks or activities in the project.a.Slackb.Nodesc.Critical Pathd.Duration
A project manager can note any action items or key points on the __________, a document that is used to communicate the progress of the project over time.a.)status reportb.)feedback channelc.)project logd.)project timeline
Upgrade your grade with Knowee
Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.