Sangeetha Bijlani can complete a work in 16 days working 10 hours per day. Sahithya can complete the same work in 18 days working 8 hours per day. If both of them work together working 9 hours per day, in how many days can they complete the work?
Question
Sangeetha Bijlani can complete a work in 16 days working 10 hours per day. Sahithya can complete the same work in 18 days working 8 hours per day. If both of them work together working 9 hours per day, in how many days can they complete the work?
Solution
Sure, let's solve this step by step.
Step 1: Calculate the total work done by each person.
Sangeetha Bijlani's total work = 16 days * 10 hours/day = 160 hours Sahithya's total work = 18 days * 8 hours/day = 144 hours
Since they are doing the same work, we can equate these two amounts of work. So, we can say that 160 hours of Sangeetha's work is equal to 144 hours of Sahithya's work.
Step 2: Calculate the rate at which each person works.
Sangeetha's work rate = 1 work / 160 hours = 0.00625 work/hour Sahithya's work rate = 1 work / 144 hours = 0.00694 work/hour
Step 3: Calculate the combined work rate when both work together.
Combined work rate = Sangeetha's work rate + Sahithya's work rate = 0.00625 work/hour + 0.00694 work/hour = 0.01319 work/hour
Step 4: Calculate the time it takes for them to complete the work together.
Time = Total work / Combined work rate = 1 work / 0.01319 work/hour = 75.78 hours
Since they are working 9 hours per day, the number of days they can complete the work is 75.78 hours / 9 hours/day = 8.42 days.
So, Sangeetha Bijlani and Sahithya can complete the work together in approximately 8.42 days when working 9 hours per day.
Similar Questions
Abhi and Bhanu can do a piece of work in 6 and 12 days, respectively. In how many days the work can be completed if Abhi and Bhanu work together?9 days18 days6 days4 days
Select the correct answerKareena can do a piece of work in 9 days and Karishma can do the same work in 18 days. They started the work. After 3 days Shahid joined them, who can complete alone the same whole work in 3 days. What is the total number of days in which they and completes the work?Options12 days4 days6 days8 days
Ajith can do a piece of work in 10 days and Vijay can do the same work in 15 days. They started the work together but after 6 days Ajith left. Find, in how many days Vijay can complete the remaining work.15 days20 days10 days30 days
Raj and Ram working together do a piece of work in 10 days. Raj alone can do it in 12 days. Ram alone will do the work in?Options20 days50 days60 days40 days
Select the correct answerAmit can complete a piece of work in 16 days. Rohit can complete the same piece of work in 8 days. If both of them work together in how many days can they complete the same piece of work?Options4 2/5 days6 days12 days5 1/3days
Upgrade your grade with Knowee
Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.