Consider the following time series: Year 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 Sales 4 6 5 8 9 5 4 3 7 8 On a graph, the three-year moving average (MA(3)) you calculated for the first subset of three years (i.e. 2010-2012) should be plotted on 2011 (i.e. half-way between the three years). True False
Question
Consider the following time series:
Year 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 Sales 4 6 5 8 9 5 4 3 7 8 On a graph, the three-year moving average (MA(3)) you calculated for the first subset of three years (i.e. 2010-2012) should be plotted on 2011 (i.e. half-way between the three years).
True False
Solution
False. The three-year moving average for the first subset of three years (2010-2012) should be plotted on 2012, which is the last year of the subset. The moving average is typically plotted at the end of the period it covers, not in the middle.
Similar Questions
Consider the following time series: Year 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 Sales 4 6 5 8 9 5 4 3 7 8 Calculate a three-year moving average (MA(3)) for the third subset of three years (i.e. 2012-2014). Round your final answer to two decimal places.
You can smooth a series using moving average if trend is not observed after plotting a time series data. True False
asked to calculate 3 months moving average, Is it same as the forecast example:3 month moving average for April = (jan + feb + mar)/3
The 3-month moving average forecast for semester 9 is closest to:Group of answer choices571.67423.33498.33521.67
Describe the trend you observed in the average speed over time graph.Note: You can also repeat the simulation and see if you get the same result.