When measuring percent complete in the monitoring phase of the project, it is common to limit the amount earned to Blank______ percent complete until the work package is 100 percent complete.Multiple choice question.7550 to 6080 to 90

Question

When measuring percent complete in the monitoring phase of the project, it is common to limit the amount earned to Blank______ percent complete until the work package is 100 percent complete.Multiple choice question.7550 to 6080 to 90

🧐 Not the exact question you are looking for?Go ask a question

Solution

The correct answer is 75 to 80 percent complete. This is a common practice in project management to avoid overestimating the progress of a project. It ensures that the project is not considered more complete than it actually is until all work packages are 100 percent complete.

Similar Questions

Which of the following statements correctly define the 100 percent rule for WBS?2 MarksThe project is only considered complete once all requirements defi the original scope statements have been completed.The project is only considered complete once all requirements in th approved scope baseline have been completed.The final deliverables should fully conform to product require nothing less, nothing more.The total of the work at the work package level should roll up higher levels so that nothing is left out and no extra work is perform

The best method for assigning costs to the baseline under the percent complete rule is to establish ___________ over the duration of the work package.Multiple choice question.frequent checkpointsgo/no-go decisionssequential milestones

Eclipse Energy Co. has a manufacturing process where the finished goods at the end of the period amount to 12,000 units, valued at $600,000. Additionally, there are 3,000 units in the closing work-in-progress (WIP) inventory, valued at $90,000.Calculate the percentage completion of the closing WIP, considering the following information:Finished goods: 12,000 units valued at $600,000Closing WIP: 3,000 units valued at $90,000Opening WIP: 2,000 units valued at $50,000Total production costs for the period: $700,000Number of units started during the period: 15,000 unitsQuestion 10Answera.40%b.60%c.70%d.50%

The percent complete with weighted monitoring gates rule combines subjective estimated percent complete with ____.Multiple choice question.the 50/50 rulehard, tangible monitoring pointspercent complete index actual costsstatus updates

Based on the NASA statistics on budget and schedule overrun vs. time spent on requirements process, what is the recommended amount of time to spend on the requirements stage?0 / 1 point0% of the total time spent on the project5-10% of the total time spent on the project20% of the total time spent on the projectThe same amount as you expect to spend on testing.