Knowee
Questions
Features
Study Tools

Twenty men were employed to do some work in a certain time. It was found that, after one-third of the scheduled time, only one-quarter of the total work was completed. How many more men should now be employed to complete the work in 3/4th of the originally scheduled time

Question

Twenty men were employed to do some work in a certain time. It was found that, after one-third of the scheduled time, only one-quarter of the total work was completed. How many more men should now be employed to complete the work in 3/4th of the originally scheduled time

🧐 Not the exact question you are looking for?Go ask a question

Solution

Sure, let's solve this step by step:

Step 1: Understand the problem The problem states that 20 men were employed to do some work in a certain time. After one-third of the time, only one-quarter of the work was completed. We need to find out how many more men should be employed to complete the work in 3/4th of the originally scheduled time.

Step 2: Set up the equation Let's denote the total work as W, the total time as T, and the number of men as M. According to the problem, we have the following relationships:

  • 20 men can do 1/4 of the work in 1/3 of the time, so 20 * (1/3T) = 1/4W.
  • We need to find out how many men (M) can do the remaining 3/4 of the work in the remaining 3/4 of the time, so M * (3/4T) = 3/4W.

Step 3: Solve the equation From the first equation, we can express W in terms of T: W = 20 * 3T = 60T. Substitute W into the second equation, we get M * (3/4T) = 3/4 * 60T. Simplify the equation, we get M = 60.

Step 4: Find out how many more men are needed Since originally there were 20 men, we need 60 - 20 = 40 more men to complete the work in 3/4th of the originally scheduled time.

This problem has been solved

Similar Questions

12 men can complete a piece of work in 4 days, while 15 women can complete the same work in 4 days. 6 men start working on the job and after working for 2 days, all of them stopped working. How many women should be put on the job to complete the remaining work, if it is to be completed in 3 days.(A) 15 (B) 18 (C) 22 (D) data inadequate

12 men can complete any work in 36 days. 18 women can complete the same piece of work in 60 days. 8 men and 20 women work together for 20 days. If only the women were to complete the remaining work in 4 days, then how many women would be required? 60 74 68 70

45 men can complete a work in 16 days. Six days after they started working, 30 more men joined them. How many days will they now take to complete the remaining work

20 men can complete a task in 30 days. If one man leaves the site at the end of each day, then what fraction of work will be completed?

If 3 men and 4 women can finish the work in 24 days, 4 men and 8 women can finish the same work in 15 days, in how many days will it take for one man alone to finish the same work?

1/3

Upgrade your grade with Knowee

Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.