The lowest level in work breakdown structure contains the:Group of answer choicesactivities.finite elements.atoms.work packages.
Question
The lowest level in work breakdown structure contains the:Group of answer choicesactivities.finite elements.atoms.work packages.
Solution
The lowest level in a Work Breakdown Structure (WBS) contains the:
- Work Packages: These are the smallest unit of work that a project can be broken down to when creating your WBS. Work packages are the lowest level of a WBS and are used to schedule, cost, monitor and control the project work.
Each work package represents a series of tasks that will be completed by a team or team member. They are typically defined by clear start/end dates, specific required resources, budget, and expected outputs.
So, the correct answer is "work packages".
Similar Questions
The lowest level in work breakdown structure contains the:
A typical Statement of work may contain the following, except:Group of answer choicesLocation of workAcceptance CriteriaStatement of workWork breakdown structure
The Work Breakdown Structure (WBS)Group of answer choicesBreaks down the tasks needed to complete the project into the level of detail for accurate calculation of schedule and budgetDescribes the assumptions and constraints associated with the scope of the projectInvolves a sequential breakdown of tasks to be completed for the projectDefines the major tasks needed to complete the project
A Work Breakdown Structure (WBS) identifies deliverables, activities, and tasks. Which statement describes a task? A list that identifies the logical way to progress through workTangible and measurable outcome expected from a projectWork performed to complete or manage the deliverables for a projectDiscrete work required to complete parts of a project
Which one of the following is captured in the Work Breakdown Structure (WBS)?The life cycle phasesThe logical order of tasksThe scope of the projectProject costs