In a development project, if an activity (i,j) of six days duration, starts late on 3rd day then which of thefollowing will be its latest finish time?Select correct option:9th day2nd day3rd day18th day
Question
In a development project, if an activity (i,j) of six days duration, starts late on 3rd day then which of thefollowing will be its latest finish time?Select correct option:9th day2nd day3rd day18th day
Solution
The latest finish time for an activity in a project is calculated by adding the duration of the activity to the latest start time. In this case, the activity starts late on the 3rd day and has a duration of six days.
So, to calculate the latest finish time, you add the start time to the duration:
3rd day (latest start time) + 6 days (duration) = 9th day
Therefore, the latest finish time for the activity will be the 9th day.
Similar Questions
In a project, Activity A has a duration of four days and begins on the morning of Monday the fourth. The successor Activity, B, has a Finish- to-Start (FS) relationship with A. The Finish-to-Start relationship has two days of lag, and Activity B has a duration of three days. If Saturday and Sunday are non-working days, which of the following statements is true?2 MarksTotal elapsed days (completing both activities) is seven daysActivity B will be completed by the end of the day on Thursday, theActivity B will be completed by the end of the day on Friday, the 15tActivity B will be completed by the end of the day on Tuesday, the 1
n a network flow diagram, two jobs (i,j) and (i,k) of ‘9’and ‘6’ days duration leaves the node ‘i’ then which ofthe following will be Late start time for ‘i’, if it is provided that both (i,j) and (i,k) finish late on 12th and 8th dayrespectively?Select correct option:6th day2nd day3rd day1st day
For an activity in a CPM analysis, the early finish time is 12 and the late finish time is 12. Which of the following statements is true? Group of answer choicesThe duration of this activity is 12.The late start is 12.The early start is 12.The activity could be on the critical path.The slack for this activity is 12.
If both jobs ‘a(l,n)’ and ‘b(m,n)’ of ‘7’ and ‘8’ days durationsrespectively, start earlier simultaneously on 4th day, then ‘n’ can start earlieron -----------day. 8th 11th 15t
Select the correct answerA can finish one-third of a work in 5 days, B can finish 2/5th of the same work in 10 days and C can finish 75% of the same work in 15 days. They work together for 6 days; The remaining work will be finished by B alone in?Options3 days5 days2.5 days1.5 days
Upgrade your grade with Knowee
Get personalized homework help. Review tough concepts in more detail, or go deeper into your topic by exploring other relevant questions.