A PCIB of 0.75 would mean ___.Multiple choice question.actual cost to date is 75% of the estimated total cost at completion.the project is over budget by 75%.the work accomplished to date represents 75% of the total budgeted dollars for the project.

Question

A PCIB of 0.75 would mean ___.Multiple choice question.actual cost to date is 75% of the estimated total cost at completion.the project is over budget by 75%.the work accomplished to date represents 75% of the total budgeted dollars for the project.

🧐 Not the exact question you are looking for?Go ask a question

Solution

The correct answer is "the work accomplished to date represents 75% of the total budgeted dollars for the project."

PCIB stands for Percent Complete Index Budgeted. It is a measure of the proportion of the total budgeted cost that has been used up by the work accomplished to date. So, a PCIB of 0.75 means that 75% of the total budgeted cost has been used up by the work done so far.

Similar Questions

Which value for TCPI indicates the project is under budget?Multiple choice question.0.781.001.78

______ is the percent complete times the original budget; also known as the budgeted cost of work performed.Multiple choice question.CVEVSVPV

What is the best way to explain "a CPI of 0.70"?Multiple choice question.70% of the project's budget has been spent.$0.70 worth of planned work has been completed for each $1.00 actually spent.$0.70 has been spent for each $1.00 worth of work completed.

Which type of project cost estimate is the most accurate?a.Order of magnitudeb.Preliminaryc.Conceptuald.Definitive

Which of the following describes the Actual budgeting method? Does not include overhead costsConsiders historical budgetsAllows for cost overagesEstimates a value for each project activity