12 girls can do a a piece of work in 30 days, working 8 hours a day . In how many days 18 girls can do the same piece of work while working 4 hours a day?

Question

12 girls can do a a piece of work in 30 days, working 8 hours a day . In how many days 18 girls can do the same piece of work while working 4 hours a day?

🧐 Not the exact question you are looking for?Go ask a question

Solution

To solve this problem, we first need to find out the total hours required to complete the work by 12 girls.

Step 1: Total hours required by 12 girls to complete the work = Number of girls * Number of days * Hours per day = 12 girls * 30 days * 8 hours/day = 2880 hours

This means that the work requires 2880 hours to be completed by one girl.

Step 2: Find out how many hours 18 girls can work in a day = Number of girls * Hours per day = 18 girls * 4 hours/day = 72 hours

This means that 18 girls can work a total of 72 hours in a day.

Step 3: Find out the number of days required for 18 girls to complete the work = Total hours required to complete the work / Hours that can be worked by 18 girls in a day = 2880 hours / 72 hours/day = 40 days

So, 18 girls can complete the work in 40 days if they work 4 hours a day.

This problem has been solved

Similar Questions

12 men can complete any work in 36 days. 18 women can complete the same piece of work in 60 days. 8 men and 20 women work together for 20 days. If only the women were to complete the remaining work in 4 days, then how many women would be required? 60 74 68 70

Sixteen men can complete a work in 22 days working 12 hours a day.  In how many days can 24 men complete the same work working 16 hours a day?

8 men and 2 women together can finish a piece of work in 24 days. In how much time will 40 men and45 women together complete 1.5 times the work, if the work done by 16 men in 8 hours is equal to thework done by 2 women in 24 hours?Question 1Answera.10b.9c.3d.6

12 men can complete a piece of work in 4 days, while 15 women can complete the same work in 4 days. 6 men start working on the job and after working for 2 days, all of them stopped working. How many women should be put on the job to complete the remaining work, if it is to be completed in 3 days.(A) 15 (B) 18 (C) 22 (D) data inadequate

Four men and two women can do a piece of work together in one day. If a woman is twice as efficient as a man, in how many days can a woman working alone do the work?

1/3