A and B can do a piece of work in 20 days, B and C can do it in 60 days. If B alone can do it in 90 days, in how many days will A and C do it together?
Question
A and B can do a piece of work in 20 days, B and C can do it in 60 days. If B alone can do it in 90 days, in how many days will A and C do it together?
Solution
Sure, let's solve this step by step:
Step 1: Find the work done by A and B together in one day. Since A and B can complete the work in 20 days, they can do 1/20 of the work in one day.
Step 2: Similarly, find the work done by B and C together in one day. Since B and C can complete the work in 60 days, they can do 1/60 of the work in one day.
Step 3: Find the work done by B alone in one day. Since B can complete the work in 90 days, B can do 1/90 of the work in one day.
Step 4: Now, we know that (work done by A and B in one day) + (work done by B and C in one day) = (work done by A, B, and C in one day) + 2*(work done by B in one day).
So, 1/20 + 1/60 = (work done by A, B, and C in one day) + 2*(1/90).
Solving this equation gives us the work done by A, B, and C in one day as 1/15.
Step 5: We know that (work done by A, B, and C in one day) = (work done by A and C in one day) + (work done by B in one day).
So, 1/15 = (work done by A and C in one day) + 1/90.
Solving this equation gives us the work done by A and C in one day as 1/18.
Step 6: Therefore, A and C together can complete the work in 18 days.
Similar Questions
A, B and C can do a piece of work in 20, 30 and 60 days respectively. In how many days can A do the work if B and C assist him on every third day?
A can do a piece of work in 5 days and B in 20 days. They work together for 2 days and then both leave the work. Then C alone can finish the remaining work in 6 days. In how many days will C finish the full work?
A can do a piece of work in 80 days. He works on it for 10 days and then B alone finishes the remaining work in 42 days. In how much time will A and B working together, finish the work?A 40 days B 30 days C 60 days D 50 days
9) A & B can do a piece of work in 72 days, B & C can do it in 120 days and A & C can do in in 90 days. In how many days all three together can do the work?
A and B together can complete a piece of work in 35 days, while A alone can complete it in 60 days. So, B alone can complete the work in how many days?